| Project | AMRUT-Integrated Calicut Water Supply Project Phase-2,Laying Diistribution Lines in cheruvanoor zone |
|---|---|
| Project Code | CLTGOI0118511P2 |
| Type | Package |
| Main Project | AMRUT-Integrated Calicut Water Supply Project Phase-2,Laying Distribution Lines in 10 Zone in Kozhikode corporation |
| Funding Agency | AMRUT |
| Category | AMRUT |
| Type of scheme | Water Supply |
| Scheme | AMRUT |
| Description | AMRUT-Integrated Calicut Water Supply Project Phase-2,Laying Diistribution Lines in cheruvanoor zone |
| Status | Completed |
| District | Kozhikkode |
| Executing Office | Kozhikode Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 27400000 |
| TS Number | TS/2682/2018-2019 |
| Technical specification | Scope of work-Supplying and Laying 75 mm PVC Pipe-22069m 65 mm GI Pipe-900m |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 08/11/2018 |
|---|---|
| Scheduled date of Completion as per agreement | 18 Oct 2019 |
| Expected date of Completion | 28/01/2020 |
| AS Date | 01 Jan 2018 |
|---|---|
| TS Date | 02 Nov 2018 |
| Estimate Approval | 02 Nov 2018 |
| NIT Approval | 05 Nov 2018 |
| Supplying and Laying | 06 Nov 2018 |
| Tender Closing | 30 Nov 2018 |
| Price bid opening | 04 Dec 2018 |
| CE Approval | 13 Dec 2018 |
|---|---|
| Final Approval | 13 Dec 2018 |
| Workorder Date | 19 Dec 2018 |
| NA | 04 Jan 2019 |
| Kozhikode Project Dn AE5 |
| Date: 22/09/2021 |
Work has been completed | 100% Completed
Work completed, Total expenditure Rs.16081647/- final Bill paid to contractor on 14.10.2020 including Road restoration charges ..
| Kozhikode Project Dn AE2 |
| Date: 21/04/2021 |
Work has been completed | 100% Completed
work completed.