Project | AMRUT - Construction of 40 LL OHSR at Kaloor |
---|---|
Project Code | EKMAMRUT1117880 |
Type | Main project |
Funding Agency | AMRUT |
Category | AMRUT |
Type of scheme | Water Supply |
Scheme | AMRUT |
Description | Construction of 40 LL OHSR at Kaloor |
Status | On-going |
District | Ernakulam |
Executing Office | Kochi Project Division |
AS Amount (Rs) | 242700000 |
AS Number | G.O.(Rt)1952/2021/LSGD & GO (Rt)No.3530/2017/LSGD 02.11.2017 |
TS Amount (Rs) | 247000000 |
TS Number | TS/CE/CR/KWA/D2/JNR/870/2019 |
Total Bill Submitted (Rs) | 139157000 |
Total Bill Paid (Rs) | 139157000 |
Population Benefitted | 86710 |
Capacity in MLD | 38.00 |
Actual Project Completion Date | 31 Jul 2022 |
Coverage | Kochi corporation Div. no. 43(part), 44(part), 64(part), 65, 70(part), 71(part), 34(part), 35,37, 38, 40, 63(part) & 39 |
Implementation Schedule | Download |
Work Plan | Download |
Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
16 Aug 2022 | Estimate of transmission main to sump is under scrutiny at CE(CR) | Kochi Project -AEE 3 | |
10 Aug 2022 | Estimate is under scrutiny at CE(CR) office for obtaining TS. | Kochi JNURM Projects AE-6 | |
06 Aug 2022 | Estimate is under srutiny at CE(CR) office for obtaining TS. | Kochi JNURM Projects AE-6 | |
02 Aug 2022 | Estimate preparation is processing for obtaining TS. | Kochi JNURM Projects AE-6 | |
26 May 2022 | Kaloor OHSR Pump house outside painting work on progress. | Kochi JNURM Projects AE-6 |
Date of start of Project | 14/10/2019 |
---|---|
Scheduled date of Completion of the Project | 10 Oct 2020 |
Expected date of Completion | 31/01/2024 |
AS Date | 08 Oct 2021 |
---|---|
TS Date | 16 Mar 2019 |
Project Officers | View |
---|