Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM 2021-22- Phase II - Ernakulam district - Providing FHTC in Alangad panchayath of Ernakulam District.

Project JJM 2021-22- Phase II - Ernakulam district - Providing FHTC in Alangad panchayath of Ernakulam District.
Project Code EKMJJM022211013P1
Type Package
Main Project JJM 2021-22- Phase II - Ernakulam district - Providing FHTC in Alangad panchayath of Ernakulam District.
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM 2021-22- Phase II - Ernakulam district - Providing FHTC in Alangad panchayath of Ernakulam District.
Status On-going
District Ernakulam
Executing Office Kochi Project Division
Agreement Number
Agreement Date
TS Amount (Rs) 562900000
TS Number ORDER No. TS/2022-2023/2021/11892
Technical specification Providing FHTC in alangad Pt

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 05/09/2023
Scheduled date of Completion as per agreement 20 Jul 2024
Expected date of Completion 20/07/2024

Processing Dates

TS Date 02 Jun 2022
Estimate Approval 02 Jun 2022
NIT Approval 07 Jun 2022
Tender Closing 28 Jun 2022
Technichal Pre-Qualification 17 Jun 2022
Price bid opening 30 Jun 2022

Approval Dates

Workorder Date 08 Jun 2023
NA 11 Jul 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kochi JNURM Projects AE-6
Date: 26/06/2024

Work in progress | 22% Completed

Ward 17 - Tile Restoration Work on progress. .

Attached images

img

Kochi JNURM Projects AE-6
Date: 25/06/2024

Work in progress | 22% Completed

Ward 16 - Tile Restoration Work on progress..

Attached images

img