Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan Mission (JJM -5th SWSM) CWSS to Vazhappally, Thrikodithanam, Paippadu, Kurichy & Changanasserry Municipality - Construction of 22 MLD Water treatment Plant at Morkulangara including alied works

Project Jal Jeevan Mission (JJM -5th SWSM) CWSS to Vazhappally, Thrikodithanam, Paippadu, Kurichy & Changanasserry Municipality - Construction of 22 MLD Water treatment Plant at Morkulangara including alied works
Project Code KTMJJM052215250P1
Type Package
Main Project Jal Jeevan Mission (JJM -5th SWSM) CWSS to Vazhappally, Thrikodithanam, Paippadu, Kurichy & Changanasserry Municipality - Construction of 22 MLD Water treatment Plant at Morkulangara including alied works
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Jal Jeevan Mission (JJM -5th SWSM) CWSS to Vazhappally, Thrikodithanam, Paippadu, Kurichy & Changanasserry Municipality - Construction of 22 MLD Water treatment Plant at Morkulangara including alied works
Status On-going
District Kottayam
Executing Office Changanassery Sn
Agreement Number
Agreement Date
TS Amount (Rs) 335200000
TS Number WRD/KWA-CE(SR)/EST_TS/19276/2023_5_1_1
Technical specification Construction of 22 MLD WTP and alied works
Contractor Chicago Constructions International Pvt Ltd (Mob: 9447111906)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 13/05/2022
Scheduled date of Completion as per agreement 21 May 2025
Expected date of Completion 21/05/2025

Processing Dates

TS Date 19 Aug 2023
Estimate Approval 19 Aug 2023
NIT Approval 19 Aug 2023
Tender Closing 10 Oct 2023
Technichal Pre-Qualification 11 Oct 2023
Price bid opening 20 Oct 2023

Approval Dates

Workorder Date 31 Oct 2023
NA 22 Nov 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Changanaserry PH Sn - AE
Date: 10/03/2025

Work in progress | 4% Completed

• 700 mm Pile 48/48 completed • 800 mm Pile 59/59 completed • 900 mm Pile 44/44 completed • Earthwork removal for sump is in progress. • Chipping of 86 nos of pile is completed. Pile test completed on one pile and Balance work is in progress. .

Changanaserry PH Sn - AE
Date: 02/03/2025

Work in progress | 4% Completed

• 700 mm Pile 48/48 completed • 800 mm Pile 59/59 completed • 900 mm Pile 44/44 completed • Earthwork removal for sump is in progress. • Chipping of 86 nos of pile is completed. Pile test completed on one pile and Balance work is in progress. .