Jal Jeevan Mission (JJM -5th SWSM) CWSS to Vazhappally, Thrikodithanam, Paippadu, Kurichy & Changanasserry Municipality - Construction of 22 MLD Water treatment Plant at Morkulangara including alied works
Project |
Jal Jeevan Mission (JJM -5th SWSM) CWSS to Vazhappally, Thrikodithanam, Paippadu, Kurichy & Changanasserry Municipality - Construction of 22 MLD Water treatment Plant at Morkulangara including alied works |
Project Code |
KTMJJM052215250P1 |
Type |
Package |
Main Project |
Jal Jeevan Mission (JJM -5th SWSM) CWSS to Vazhappally, Thrikodithanam, Paippadu, Kurichy & Changanasserry Municipality - Construction of 22 MLD Water treatment Plant at Morkulangara including alied works
|
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-01 |
Description |
Jal Jeevan Mission (JJM -5th SWSM) CWSS to Vazhappally, Thrikodithanam, Paippadu, Kurichy & Changanasserry Municipality - Construction of 22 MLD Water treatment Plant at Morkulangara including alied works |
Status |
On-going |
District |
Kottayam |
Executing Office |
Changanassery Sn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
335200000 |
TS Number |
WRD/KWA-CE(SR)/EST_TS/19276/2023_5_1_1 |
Technical specification |
Construction of 22 MLD WTP and alied works |
Contractor |
Chicago Constructions International Pvt Ltd (Mob: 9447111906) |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
13/05/2022 |
Scheduled date of Completion as per agreement |
21 May 2025 |
Expected date of Completion |
21/05/2025 |
Processing Dates
TS Date |
19 Aug 2023 |
Estimate Approval |
19 Aug 2023 |
NIT Approval |
19 Aug 2023 |
Tender Closing |
10 Oct 2023 |
Technichal Pre-Qualification |
11 Oct 2023 |
Price bid opening |
20 Oct 2023 |
Approval Dates
Workorder Date |
31 Oct 2023 |
NA |
22 Nov 2023 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Changanaserry PH Sn - AE |
Date: 10/03/2025 |
Work in progress | 4% Completed
• 700 mm Pile 48/48 completed • 800 mm Pile 59/59 completed • 900 mm Pile 44/44 completed • Earthwork removal for sump is in progress. • Chipping of 86 nos of pile is completed. Pile test completed on one pile and Balance work is in progress.
.
Changanaserry PH Sn - AE |
Date: 02/03/2025 |
Work in progress | 4% Completed
• 700 mm Pile 48/48 completed • 800 mm Pile 59/59 completed • 900 mm Pile 44/44 completed • Earthwork removal for sump is in progress. • Chipping of 86 nos of pile is completed. Pile test completed on one pile and Balance work is in progress.
.