AMRUT-AMRUT - Laying Transmission Main and sewer networks in Block L -Collection and Conveyance system -Laying of 315mm dia HDPE Transmission main from Ulloor Jn to SN Jn in ULLOOR- AKULAM Road by HDD method.-Sewerage Work
Project |
AMRUT-AMRUT - Laying Transmission Main and sewer networks in Block L -Collection and Conveyance system -Laying of 315mm dia HDPE Transmission main from Ulloor Jn to SN Jn in ULLOOR- AKULAM Road by HDD method.-Sewerage Work |
Project Code |
TVMAMRUT 2020315382 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Sewerage |
Scheme |
AMRUT |
Description |
AMRUT-AMRUT - Laying Transmission Main
and sewer networks in Block L -Collection and
Conveyance system -Laying of 315mm dia
HDPE Transmission main from Ulloor Jn to
SN Jn in ULLOOR- AKULAM Road by HDD
method.-Sewerage Work |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Trivandrum Project Dn |
AS Amount (Rs) |
49100000
|
AS Number |
G.O.(Rt)No.1087/2023/LSGD |
TS Amount (Rs) |
30200000 |
TS Number |
8266/2023-2024 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
Date is not specified |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT-AMRUT - Laying Transmission Main and sewer networks in Block L -Collection and Conveyance system -Laying of 315mm dia HDPE Transmission main from Ulloor Jn to SN Jn in ULLOOR- AKULAM Road by HDD method.-Sewerage Work |
Trivandrum Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
13 May 2024 |
Pipe supplied on 05/10/2023. 315mm HDPE pipe 615m pulled, out of 840m. Manhole construction progressing in various locations.MH cleaning in progress. |
Thiruvananthapuram Project AE9 |
|
08 May 2024 |
Pipe supplied on 05/10/2023. 315mm HDPE pipe 615m pulled, out of 840m. Manhole construction progressing in various locations. |
Thiruvananthapuram Project AE9 |
|
02 Apr 2024 |
Pipe supplied on 05/10/2023. 315mm HDPE pipe 615m pulled, out of 840m. Manhole construction progressing in various locations. |
Thiruvananthapuram Project AE9 |
|
30 Mar 2024 |
Pipe supplied on 05/10/2023. 315mm HDPE pipe 615m pulled, out of 840m. Manhole construction progressing in various locations. |
Thiruvananthapuram Project AE9 |
|
25 Mar 2024 |
Pipe supplied on 05/10/2023. 315mm HDPE pipe 615m pulled, out of 840m. Manhole construction progressing in various locations. |
Thiruvananthapuram Project AE9 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
10/07/2023 |
Scheduled date of Completion of the Project |
Date is not specified |
Expected date of Completion |
24/07/2024 |
Processing Dates
AS Date |
10 May 2023 |
TS Date |
10 Jul 2023 |