JAL JEEVAN MISSION - Pipe line extension , Replacement of Ac pipe ,Renovation of existing pump house and sump, DI pumping and distribution lines ,Supply and erection of pump set and providing FHTC in Nilamel Panchayath - Phase II

Project JAL JEEVAN MISSION - Pipe line extension , Replacement of Ac pipe ,Renovation of existing pump house and sump, DI pumping and distribution lines ,Supply and erection of pump set and providing FHTC in Nilamel Panchayath - Phase II
Project Code KLMJJM08204220P1
Type Package
Main Project JAL JEEVAN MISSION - Pipe line extension , Replacement of Ac pipe ,Renovation of existing pump house and sump, DI pumping and distribution lines ,Supply and erection of pump set and providing FHTC in Nilamel Panchayath - Phase II
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Pipe line extension , Replacement of Ac pipe ,Renovation of existing pump house and sump, DI pumping and distribution lines ,Supply and erection of pump set and providing FHTC in Nilamel Panchayath
Status On-going
District Kollam
Executing Office Kadakkal PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 197590000
TS Number TS/2021-2022/2020/20573 Dated: 26-05-2021
Technical specification Pipe line extension , Replacement of Ac pipe ,Renovation of existing pump house and sump, DI pumping and distribution lines ,Supply and erection of pump set and providing FHTC in Nilamel Panchayath
Contractor Sohail shamsudeen (Mob: 9809509114)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 04/10/2022
Scheduled date of Completion as per agreement 30 Mar 2023
Expected date of Completion 01/07/2023

Processing Dates

TS Date 26 May 2021
Estimate Approval 26 May 2021
NIT Approval 30 May 2022
Tender Closing 30 Jun 2022
Technichal Pre-Qualification 30 Jun 2022
Price bid opening 30 Jun 2022

Approval Dates

Workorder Date 17 Sep 2022
NA 26 Sep 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kadakkal PH Sn - AE
Date: 04/04/2026

Work in progress | 99% Completed

same status.

Kadakkal PH Sn - AE
Date: 30/03/2026

Work in progress | 99% Completed

samestatus.