Deposit work - Pavithreswaram Grama Panchayath for the financial year 2021-22 - ARWSS to Kulakkada and Pavithreswaram-Line extension at various wards of Pavithreswaram Grama Panchayath

Project Deposit work - Pavithreswaram Grama Panchayath for the financial year 2021-22 - ARWSS to Kulakkada and Pavithreswaram-Line extension at various wards of Pavithreswaram Grama Panchayath
Project Code KLMDEPO042211067P1
Type Package
Main Project Deposit work - Pavithreswaram Grama Panchayath for the financial year 2021-22 - ARWSS to Kulakkada and Pavithreswaram-Line extension at various wards of Pavithreswaram Grama Panchayath
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Deposit work - Pavithreswaram Grama Panchayath for the financial year 2021-22 - ARWSS to Kulakkada and Pavithreswaram-Line extension at various wards of Pavithreswaram Grama Panchayath
Status On-going
District Kollam
Executing Office Kottarakkara PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 2145430
TS Number 1058/2022-2023
Technical specification Line extension at various wards of Pavithreswaram Grama Panchayathu
Contractor SUNDER LAL (Mob: 9447154889)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 01/06/2022
Scheduled date of Completion as per agreement 17 Aug 2022
Expected date of Completion 24/09/2022

Processing Dates

TS Date 18 Apr 2022
Estimate Approval 18 Apr 2022
NIT Approval 18 Apr 2022
Tender Closing 30 Apr 2022
Price bid opening 03 May 2022

Approval Dates

Workorder Date 04 May 2022
NA 18 May 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kottarakkara PH Sn - AE
Date: 01/09/2025

Work has been completed | 100% Completed

completed.

Kottarakkara PH Sn - AE
Date: 01/03/2023

Work has been completed | 100% Completed

Work completed.