Project | Jal Jeevan Mission 2021-22- Providing FHTCs (240nos) and line extension in Anakkara Panchayath- Phase III |
---|---|
Project Code | PKDJJM022212204P1 |
Type | Package |
Main Project | Jal Jeevan Mission 2021-22- Providing FHTCs (240nos) and line extension in Anakkara Panchayath- Phase III |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission 2021-22- Providing FHTCs (240nos) and line extension in Anakkara Panchayath- Phase III |
Status | On-going |
District | Palakkad |
Executing Office | Shoranur Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 36700000 |
TS Number | TS/2022-2023/2021/26806 |
Technical specification | Providing FHTCs (240nos) and line extension in Anakkara Panchayath- Phase III |
Contractor | VELAYUDHAN M (Mob: 9447335838) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 22/06/2022 |
---|---|
Scheduled date of Completion as per agreement | 07 Dec 2022 |
Expected date of Completion | 31/03/2024 |
TS Date | 29 Apr 2022 |
---|---|
Estimate Approval | 29 Apr 2022 |
NIT Approval | 26 Apr 2022 |
Tender Closing | 05 May 2022 |
Price bid opening | 09 May 2022 |
Workorder Date | 08 Jun 2022 |
---|---|
NA | 22 Jun 2022 |
Shoranur PH Sn AE |
Date: 01/07/2024 |
Work has been completed | 100% Completed
Work has been completed .
Shoranur PH Sn AE |
Date: 28/06/2024 |
Work has been completed | 100% Completed
Work Completed..