Jal Jeevan Mission 2021-22- Providing FHTCs (240nos) and line extension in Anakkara Panchayath- Phase III

Project Jal Jeevan Mission 2021-22- Providing FHTCs (240nos) and line extension in Anakkara Panchayath- Phase III
Project Code PKDJJM022212204P1
Type Package
Main Project Jal Jeevan Mission 2021-22- Providing FHTCs (240nos) and line extension in Anakkara Panchayath- Phase III
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission 2021-22- Providing FHTCs (240nos) and line extension in Anakkara Panchayath- Phase III
Status On-going
District Palakkad
Executing Office Shoranur Sn
Agreement Number
Agreement Date
TS Amount (Rs) 36700000
TS Number TS/2022-2023/2021/26806
Technical specification Providing FHTCs (240nos) and line extension in Anakkara Panchayath- Phase III
Contractor VELAYUDHAN M (Mob: 9447335838)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 22/06/2022
Scheduled date of Completion as per agreement 07 Dec 2022
Expected date of Completion 31/03/2024

Processing Dates

TS Date 29 Apr 2022
Estimate Approval 29 Apr 2022
NIT Approval 26 Apr 2022
Tender Closing 05 May 2022
Price bid opening 09 May 2022

Approval Dates

Workorder Date 08 Jun 2022
NA 22 Jun 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Shoranur PH Sn AE
Date: 01/07/2024

Work has been completed | 100% Completed

Work has been completed .

Shoranur PH Sn AE
Date: 28/06/2024

Work has been completed | 100% Completed

Work Completed..