Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM - Kannur District - WSS to Ulikkal Panchayath - Construction of WTP and Reservoirs, Supplying and laying pumping main, transmission mains and distribution network, Supply and erection of pump sets and providing FHTCs in Ulikkal Panchayath

Project JJM - Kannur District - WSS to Ulikkal Panchayath - Construction of WTP and Reservoirs, Supplying and laying pumping main, transmission mains and distribution network, Supply and erection of pump sets and providing FHTCs in Ulikkal Panchayath
Project Code KNRJJM022213302
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description JJM - Kannur District - WSS to Ulikkal Panchayath - Construction of WTP and Reservoirs, Supplying and laying pumping main, transmission mains and distribution network, Supply and erection of pump sets and providing FHTCs in Ulikkal Panchayath
Status On-going
District Kannur
Executing Office Thaliparambu WS Dn
AS Amount (Rs) 1490000000
AS Number G.O (Rt)No.134/2022/WRD
TS Amount (Rs) 1279700000
TS Number WRD/KWA-CE(NR)/EST_TS/1314/2022_5_24_23
Total Bill Submitted (Rs) 388897880
Total Bill Paid (Rs)
Population Benefitted 35429
Capacity in MLD 4.00
Actual Project Completion Date Date is not specified
Coverage 8919 FHTCs
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)-Jal Jeevan Mission - Kannur District - Ulikkal Panchayath - Laying distribution network and providing functional household tap connection in Ulikkal Grama Panchayath-WSS to Ulikkal Panchayath - Package-III - Supplying and laying Gravity main and Pumping main, Construction of 4.00 LL OHSR at Angadisserithattu, Construction of BP Tank, Construction of sump cum pump house at Angadisseri, supply and errection of C.F. pumpsets, LSGD road reformation work, Supplying and laying distribution network for Zone-III and providing FHTCs-General Civil Work Irikkur WS Sn
2 Jal Jeevan Mission (JJM)-Jal Jeevan Mission - Kannur District - Ulikkal Panchayath - Laying distribution network and providing functional household tap connection in Ulikkal Grama Panchayath-WSS to Ulikkal Panchayath - Package-II - Supplying and laying pumping main from Booster station at Anakkuzhi to OHSR at Kolithattu, Construction of 7.00LL OHSR at Kolithattu, supplying and laying distibution network for Zone-II and providing FHTCs, LSGD road reformation works and PWD, KSTP, PMGSY road reformation works-Pipeline Work Irikkur WS Sn
3 Jal Jeevan Mission (JJM)-Jal Jeevan Mission - Kannur District - Ulikkal Panchayath - Laying distribution network and providing functional household tap connection in Ulikkal Grama Panchayath-WSS to Ulikkal Panchayath - Package-I - Supplying and laying pumping main, consteruction of 7.00 LL GLSR at Thermala, Construction of 1.00 LL sump cum pump house, supplying and errection of pumpsets, LSGD road reformation works, supplying and laying distribution network for Zone-I and providing FHTCs-General Civil Work- Irikkur WS Sn
4 Jal Jeevan Mission (JJM)-Jal Jeevan Mission - Kannur District - Ulikkal Panchayath - Laying distribution network and providing functional household tap connection in Ulikkal Grama Panchayath-WSS to Ulikkal Panchayath - Package-IV - Construction of 4MLD WTP and allied components, Pumping main, Gravity main, Distribution system for Zone-IV and providing FHTCs and LSGD road reformation works-General Civil Work Irikkur WS Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
05 Mar 2025 Package 1 -Thermala OHSR – RCC work of Stair and landing completed. Pipe laying work on going, Pumping Main 1.4 Km Laid & Distribution Line 99.70 Km laid, 2514 numbers of HTC provided, BPT : reinforcement work of haunch & side wall up to 1.2m completed and shuttering work completed Package 2- Distribution Line 104.97 Km pipe laid, 1443 numbers of HTC provided. Partial quantity of DI Pipes & Valves Supplied.Package 3 - Angadisserithattu sump cum pump house – RCC works of side wall, beam and cover slab of sump completed. Angadisserithattu OHSR - site leveling works partially completed-Auction of hard rock to be conducted. Distribution Line 35.74 km pipe laid, 587 numbers of HTC provided.Package 4-Construction of civil structures completed. Plastering & Flooring work 99% completed. providing & fixing handrail, doors and window shutters are not started. Compound wall plastering not completed. Electrical & mechanical works are in progress. Renovation work of Intake well and Booster tank at anakkuzhi not started. Raw Water & Clear Water Pumping Main DI 250mm 3.085Km Laid & Total Distribution 18.1 km pipe laid, 280 numbers of HTC provided. Thaliparamba WS Dn EE
15 Feb 2025 Package 1 -Thermala OHSR – RCC work of Stair and landing completed. Pipe laying work on going, Pumping Main 1.4 Km Laid & Distribution Line 99.70 Km laid, 2514 numbers of HTC provided, BPT : reinforcement work of haunch & side wall up to 1.2m completed and shuttering work completed. Package 2- Distribution Line 104.89 Km pipe laid, 1443 numbers of HTC provided. Partial quantity of DI Pipes & Valves Supplied.Package 3 - Angadisserithattu sump cum pump house – RCC works of side wall, beam and cover slab of sump completed. Angadisserithattu OHSR - site leveling works partially completed-Auction of hard rock to be conducted. Distribution Line 34.45 km pipe laid, 587 numbers of HTC provided.Package 4-Construction of civil structures completed. Plastering & Flooring work 99% completed. providing & fixing handrail, doors and window shutters are not started. Compound wall plastering not completed. Electrical & mechanical works are in progress. Renovation work of Intake well and Booster tank at anakkuzhi not started. Raw Water & Clear Water Pumping Main DI 250mm 3.085Km Laid & Total Distribution 18.1 km pipe laid, 280 numbers of HTC provided. Thaliparamba WS Dn EE
02 Feb 2025 Package 1 -Thermala OHSR – RCC work of Stair and landing completed. Pipe laying work on going, Pumping Main 1.4 Km Laid & Distribution Line 99.70 Km laid, 2514 numbers of HTC provided, BPT : reinforcement work of haunch & side wall up to 1.2m completed and shuttering work completed. Package 2- Distribution Line 104.89 Km pipe laid, 1443 numbers of HTC provided. Partial quantity of DI Pipes & Valves Supplied.Package 3 - Angadisserithattu sump cum pump house – RCC works of side wall, beam and cover slab of sump completed. Angadisserithattu OHSR - earthwork excavation & site leveling works are going on, Distribution Line 34.45 km pipe laid, 541 numbers of HTC provided.Package 4-retaining wall -90% completed and compound wall works completed, Filter house –Tile work and Electrification works going on. Recycling tank- plastering works completed. Sump cum pump house - Plastering work completed and Electrification works going on. Chemical House- solution tank tile work completed. Clarifflocculator: launder side wall concrete completed & plastering work going on. Flash mixer: side concrete completed. Aerator-tie beam concrete completed, Concrete work of column above tie beam completed, Concrete work of central column completed. Renovation Work of Koottupuzha Intake Well – RCC work of remaining Side Wall & Covering slab of Leading Channel completed.- Raw Water & Clear Water Pumping Main DI 250mm 3.4Km Laid & Total Distribution 18.1 km pipe laid, 280 numbers of HTC provided. Thaliparamba WS Dn EE
27 Jan 2025 Package 1 -Thermala OHSR – RCC work of Stair and landing completed. Pipe laying work on going, Pumping Main 1.4 Km Laid & Distribution Line 99.27 Km laid, 2514 numbers of HTC provided, BPT : reinforcement work of haunch & side wall up to 1.2m completed and shuttering work completed. Package 2- Distribution Line 103.05 Km pipe laid, 1443 numbers of HTC provided. Partial quantity of DI Pipes & Valves Supplied.Package 3 - Angadisserithattu sump cum pump house – RCC works of side wall, beam and cover slab of sump completed. Angadisserithattu OHSR - earthwork excavation & site leveling works are going on, Distribution Line 33.45 km pipe laid, 541 numbers of HTC provided.Package 4-retaining wall -90% completed and compound wall works completed, Filter house –Tile work and Electrification works going on. Recycling tank- plastering works completed. Sump cum pump house - Plastering work completed and Electrification works going on. Chemical House- solution tank tile work completed. Clarifflocculator: launder side wall concrete completed & plastering work going on. Flash mixer: side concrete completed. Aerator-tie beam concrete completed, Concrete work of column above tie beam completed, Concrete work of central column completed. Renovation Work of Koottupuzha Intake Well – RCC work of remaining Side Wall & Covering slab of Leading Channel completed.- Raw Water & Clear Water Pumping Main DI 250mm 3.4Km Laid & Total Distribution 18.1 km pipe laid, 280 numbers of HTC provided. Thaliparamba WS Dn EE
21 Jan 2025 Package 1 -Thermala OHSR – RCC work of Stair and landing completed. Pipe laying work on going, Pumping Main 1.4 Km Laid & Distribution Line 98.92 Km laid, 2514 numbers of HTC provided, BPT : reinforcement work of haunch & side wall up to 1.2m completed and shuttering work completed. Package 2- Distribution Line 100.91 Km pipe laid, 1418 numbers of HTC provided. Partial quantity of DI Pipes & Valves Supplied.Package 3 - Angadisserithattu sump cum pump house – RCC works of side wall, beam and cover slab of sump completed. Angadisserithattu OHSR - earthwork excavation & site leveling works are going on, Distribution Line 32.49 km pipe laid, 521 numbers of HTC provided.Package 4-retaining wall -90% completed and compound wall works completed, Filter house –Tile work and Electrification works going on. Recycling tank- plastering works completed. Sump cum pump house - Plastering work completed and Electrification works going on. Chemical House- solution tank tile work completed. Clarifflocculator: launder side wall concrete completed & plastering work going on. Flash mixer: side concrete completed. Aerator-tie beam concrete completed, Concrete work of column above tie beam completed, Concrete work of central column completed. Renovation Work of Koottupuzha Intake Well – RCC work of remaining Side Wall & Covering slab of Leading Channel completed.- Raw Water & Clear Water Pumping Main DI 250mm 3.4Km Laid & Total Distribution 18.1 km pipe laid, 280 numbers of HTC provided Thaliparamba WS Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 23/02/2022
Scheduled date of Completion of the Project 31 Dec 2023
Expected date of Completion 31/12/2024

Processing Dates

AS Date 23 Feb 2022
TS Date 31 Mar 2023

Other details

Project Officers View