JJM - Kannur District - WSS to Ulikkal Panchayath - Construction of WTP and Reservoirs, Supplying and laying pumping main, transmission mains and distribution network, Supply and erection of pump sets and providing FHTCs in Ulikkal Panchayath
Project |
JJM - Kannur District - WSS to Ulikkal Panchayath - Construction of WTP and Reservoirs, Supplying and laying pumping main, transmission mains and distribution network, Supply and erection of pump sets and providing FHTCs in Ulikkal Panchayath |
Project Code |
KNRJJM022213302 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM - Kannur District - WSS to Ulikkal Panchayath - Construction of WTP and Reservoirs, Supplying and laying pumping main, transmission mains and distribution network, Supply and erection of pump sets and providing FHTCs in Ulikkal Panchayath |
Status |
On-going |
District |
Kannur |
Executing Office |
Thaliparambu WS Dn |
AS Amount (Rs) |
1490000000
|
AS Number |
G.O (Rt)No.134/2022/WRD |
TS Amount (Rs) |
124700000 |
TS Number |
WRD/KWA-CE(NR)/EST_TS/1314/2022_5_24_23 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
35429 |
Capacity in MLD |
4.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
8919 FHTCs |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM)-Jal Jeevan Mission - Kannur District - Ulikkal Panchayath - Laying distribution network and providing functional household tap connection in Ulikkal Grama Panchayath-WSS to Ulikkal Panchayath - Package-III - Supplying and laying Gravity main and Pumping main, Construction of 4.00 LL OHSR at Angadisserithattu, Construction of BP Tank, Construction of sump cum pump house at Angadisseri, supply and errection of C.F. pumpsets, LSGD road reformation work, Supplying and laying distribution network for Zone-III and providing FHTCs-General Civil Work |
Irikkur WS Sn |
|
2 |
Jal Jeevan Mission (JJM)-Jal Jeevan Mission - Kannur District - Ulikkal Panchayath - Laying distribution network and providing functional household tap connection in Ulikkal Grama Panchayath-WSS to Ulikkal Panchayath - Package-II - Supplying and laying pumping main from Booster station at Anakkuzhi to OHSR at Kolithattu, Construction of 7.00LL OHSR at Kolithattu, supplying and laying distibution network for Zone-II and providing FHTCs, LSGD road reformation works and PWD, KSTP, PMGSY road reformation works-Pipeline Work |
Irikkur WS Sn |
|
3 |
Jal Jeevan Mission (JJM)-Jal Jeevan Mission - Kannur District - Ulikkal Panchayath - Laying distribution network and providing functional household tap connection in Ulikkal Grama Panchayath-WSS to Ulikkal Panchayath - Package-I - Supplying and laying pumping main, consteruction of 7.00 LL GLSR at Thermala, Construction of 1.00 LL sump cum pump house, supplying and errection of pumpsets, LSGD road reformation works, supplying and laying distribution network for Zone-I and providing FHTCs-General Civil Work- |
Irikkur WS Sn |
|
4 |
Jal Jeevan Mission (JJM)-Jal Jeevan Mission - Kannur District - Ulikkal Panchayath - Laying distribution network and providing functional household tap connection in Ulikkal Grama Panchayath-WSS to Ulikkal Panchayath - Package-IV - Construction of 4MLD WTP and allied components, Pumping main, Gravity main, Distribution system for Zone-IV and providing FHTCs and LSGD road reformation works-General Civil Work |
Irikkur WS Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
18 May 2024 |
Package 1 -Thermala OHSR – Shuttering work of Side Wall Completed. Shuttering works of roof beam & Slab going on. Pipe laying work on going, 78.30km layed, 2120 number HTC provided. Package 2- 65.36Km pipe laid, 1160 number HTC provided. Package 3 - Angadisserithattu sump cum pump house – RCC works of side wall, beam and slab completed. Angadisserithattu OHSR - earthwork excavation & site leveling works are going on Package 3- 25.63 km pipe layed, 481 number HTC provided. Package 4-retaining wall -90% completed, Filter house –Laterite masonry & Plastering work going on, Pipe gallery control chamber, clear water channel & Waste water Channel side wall RCC work completed. Wash Water Tank side wall reinforcement works going on. Recycling tank- plastering works completed. Sump cum pump house - Plastering work completed. Chemical House- Laterite masonry work 90% completed., RCC of solution tank side wall also completed. Clarifflocculator: Exterior plastering work completed. Flash mixer: side concrete completed. Aerator-RCC work of 6 columns up to 2m completed. Renovation Work of Koottupuzha Intake Well – RCC work of remaining Side Wall & Covering slab of Leading Channel completed.- Package 4- 17.68 km pipe layed, 710 number HTC provided. |
Thaliparamba WS Dn EE |
|
13 May 2024 |
Package 1 -Thermala OHSR – Shuttering work of Side Wall Completed. Shuttering works of roof beam & Slab going on. Pipe laying work on going, 78.30km layed, 2120 number HTC provided. Package 2- 65.36Km pipe laid, 1160 number HTC provided. Package 3 - Angadisserithattu sump cum pump house – RCC works of side wall, beam and slab completed. Angadisserithattu OHSR - earthwork excavation & site leveling works are going on Package 3- 25.63 km pipe layed, 481 number HTC provided. Package 4-retaining wall -90% completed, Filter house –Laterite masonry & Plastering work going on, Pipe gallery control chamber, clear water channel & Waste water Channel side wall RCC work completed. Wash Water Tank side wall reinforcement works going on. Recycling tank- plastering works completed. Sump cum pump house - Plastering work completed. Chemical House- Laterite masonry work 90% completed., RCC of solution tank side wall also completed. Clarifflocculator: Exterior plastering work completed. Flash mixer: side concrete completed. Aerator-RCC work of 6 columns up to 2m completed. Renovation Work of Koottupuzha Intake Well – RCC work of remaining Side Wall & Covering slab of Leading Channel completed.- Package 4- 17.68 km pipe layed, 710 number HTC provided. |
Thaliparamba WS Dn EE |
|
11 May 2024 |
Package 1 -Thermala OHSR – Shuttering work of Side Wall Completed. Shuttering works of roof beam & Slab going on. Pipe laying work on going, 78.30km layed, 2120 number HTC provided. Package 2- 65.36Km pipe laid, 1160 number HTC provided. Package 3 - Angadisserithattu sump cum pump house – RCC works of side wall, beam and slab completed. Angadisserithattu OHSR - earthwork excavation & site leveling works are going on Package 3- 25.63 km pipe layed, 481 number HTC provided. Package 4-retaining wall -90% completed, Filter house –Laterite masonry & Plastering work going on, Pipe gallery control chamber, clear water channel & Waste water Channel side wall RCC work completed. Wash Water Tank side wall reinforcement works going on. Recycling tank- plastering works completed. Sump cum pump house - Plastering work completed. Chemical House- Laterite masonry work 90% completed., RCC of solution tank side wall also completed. Clarifflocculator: Exterior plastering work completed. Flash mixer: side concrete completed. Aerator-RCC work of 6 columns up to 2m completed. Renovation Work of Koottupuzha Intake Well – Reinforcement work of remaining Side Wall & Covering slab of Leading Channel completed. completed.- Package 4- 17.68 km pipe layed, 710 number HTC provided. |
Thaliparamba WS Dn EE |
|
10 May 2024 |
Package 1 -Thermala OHSR – Shuttering work of Side Wall Completed. Shuttering works of roof beam & Slab going on. Pipe laying work on going, 78.30km layed, 2120 number HTC provided. Package 2- 65.36Km pipe laid, 1160 number HTC provided. Package 3 - Angadisserithattu sump cum pump house – RCC works of side wall, beam and slab completed. Angadisserithattu OHSR - earthwork excavation & site leveling works are going on Package 3- 25.63 km pipe layed, 481 number HTC provided. Package 4-retaining wall -90% completed, Filter house –Laterite masonry & Plastering work going on, Pipe gallery control chamber, clear water channel & Waste water Channel side wall RCC work completed. Wash Water Tank side wall reinforcement works going on. Recycling tank- plastering works completed. Sump cum pump house - Plastering work completed. Chemical House- Laterite masonry work 90% completed., RCC of solution tank side wall also completed. Clarifflocculator: Exterior plastering work completed. Flash mixer: side concrete completed. Aerator-RCC work of 6 columns up to 2m completed. Renovation Work of Koottupuzha Intake Well – RCC work of 1m height of Leading Channel Side wall completed.- Package 4- 17.68 km pipe layed, 710 number HTC provided. |
Thaliparamba WS Dn EE |
|
08 May 2024 |
Package 1 -Thermala OHSR – Shuttering work of Side Wall Completed. Shuttering works of roof beam & Slab going on. Pipe laying work on going, 78.30km layed, 2120 number HTC provided. Package 2- 65.36Km pipe laid, 1160 number HTC provided. Package 3 - Angadisserithattu sump cum pump house – RCC works of side wall, beam and slab completed. Angadisserithattu OHSR - earthwork excavation & site leveling works are going on Package 3- 25.63 km pipe layed, 481 number HTC provided. Package 4-retaining wall -90% completed, Filter house –Laterite masonry & Plastering work going on, Pipe gallery control chamber, clear water channel & Waste water Channel side wall RCC work completed. Wash Water Tank side wall reinforcement works going on. Recycling tank- plastering works completed. Sump cum pump house - Plastering work completed. Chemical House- Laterite masonry work 90% completed., RCC of solution tank side wall also completed. Clarifflocculator: Exterior plastering work completed. Flash mixer: side concrete completed. Aerator-RCC work of 6 columns up to 2m completed. Renovation Work of Koottupuzha Intake Well – RCC work of Leading Channel Base Slab Completed.- Package 4- 17.68 km pipe layed, 710 number HTC provided. |
Thaliparamba WS Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
23/02/2022 |
Scheduled date of Completion of the Project |
31 Dec 2023 |
Expected date of Completion |
31/03/2024 |
Processing Dates
AS Date |
23 Feb 2022 |
TS Date |
03 Jan 2023 |