Project | Jal Jeevan Mission (JJM)-Venkitengu Panchayath (Phase 3 )-JJM 2021-22-Providing line extension and balance functional house hold tap connection (FHTCs) at Venkitengu Panchayath -Pipeline work. |
---|---|
Project Code | TCRJJM022213545P1 |
Type | Package |
Main Project | Jal Jeevan Mission (JJM)-Venkitengu Panchayath (Phase 3 )-JJM 2021-22-Providing line extension and balance functional house hold tap connection (FHTCs) at Venkitengu Panchayath -Pipeline work. |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission (JJM)-Venkitengu Panchayath (Phase 3 )-JJM 2021-22-Providing line extension and balance functional house hold tap connection (FHTCs) at Venkitengu Panchayath -Pipeline work. |
Status | On-going |
District | Thrissur |
Executing Office | Guruvayur PH Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 196000000 |
TS Number | WRD/KWA-CE(CR)/EST_TS/1432/2022_26_1_1 |
Technical specification | Providing line extension and balance functional house hold tap connection (FHTCs). |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 25/01/2023 |
---|---|
Scheduled date of Completion as per agreement | 24 Oct 2023 |
Expected date of Completion | 31/07/2024 |
TS Date | 14 Oct 2022 |
---|---|
Estimate Approval | 14 Oct 2022 |
NIT Approval | 14 Oct 2022 |
Tender Closing | 22 Nov 2022 |
Technichal Pre-Qualification | 22 Nov 2022 |
Price bid opening | 24 Nov 2022 |
Workorder Date | 25 Jan 2023 |
---|---|
NA | 10 Feb 2023 |
Guruvayur PH Sn AE |
Date: 29/06/2024 |
Work in progress | 52% Completed
Total FHTCs are 3848, balance work ongoing. .
Guruvayur PH Sn AE |
Date: 24/06/2024 |
Work in progress | 52% Completed
Total FHTCs are 3848, balance work ongoing. .