Jal Jeevan Mission- Kasaragod District- RWSS to Enmakaje and adjoining Villages- Phase II - (Balance work) Shivagiri area Part I-Laying distribution and providing FHTCs -Pipe line work

Project Jal Jeevan Mission- Kasaragod District- RWSS to Enmakaje and adjoining Villages- Phase II - (Balance work) Shivagiri area Part I-Laying distribution and providing FHTCs -Pipe line work
Project Code KGDJJM08202940P6
Type Package
Main Project Jal Jeevan Mission- Kasaragod District- Enmakaje Grama Panchayath- ARWSS to Enmakaje and adjoining Villages- Phase II - Laying distribution System and providing FHTC
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Jal Jeevan Mission- Kasaragod District- RWSS to Enmakaje and adjoining Villages- Phase II - (Balance work) Shivagiri area Part I-Laying distribution and providing FHTCs -Pipe line work
Status Completed
District Kasaragod
Executing Office Bovikkanam WSP Sn
Agreement Number
Agreement Date
TS Amount (Rs) 8600000
TS Number 24872/2023-26-1-1
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 22/11/2023
Scheduled date of Completion as per agreement 21 Mar 2024
Expected date of Completion 30/01/2025

Processing Dates

TS Date 25 Oct 2023
Estimate Approval 25 Oct 2023
NIT Approval 25 Oct 2023
Tender Closing 30 Oct 2023
Technichal Pre-Qualification 30 Oct 2023
Price bid opening 31 Oct 2023

Approval Dates

Workorder Date 31 Oct 2023
NA 22 Nov 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Bovikkanam WSP Sn AE
Date: 22/10/2025

Work has been completed | 100% Completed

work completed on 20/05/2025.

Bovikkanam WSP Sn AE
Date: 18/10/2025

Work in progress | 80% Completed

Work in progress.