Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM - Kaipamangalam Panchayath PHASE I-CWSS to Nattika Firka-Providing FHTC to Rural households from ongoing scheme (MVS) including Distribution Strengthening(3432 No FHTC)

Project JJM - Kaipamangalam Panchayath PHASE I-CWSS to Nattika Firka-Providing FHTC to Rural households from ongoing scheme (MVS) including Distribution Strengthening(3432 No FHTC)
Project Code TCRJJM08205183P1
Type Package
Main Project JJM - Kaipamangalam Panchayath PHASE I-CWSS to Nattika Firka-Providing FHTC to Rural households from ongoing scheme (MVS) including Distribution Strengthening
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM - Kaipamangalam Panchayath PHASE I-CWSS to Nattika Firka-Providing FHTC to Rural households from ongoing scheme (MVS) including Distribution Strengthening(3432 No FHTC)
Status On-going
District Thrissur
Executing Office Mathilakam PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 87000000
TS Number TS/2020-2021/2020/20462
Technical specification JJM - Kaipamangalam Panchayath PHASE I-CWSS to Nattika Firka-Providing FHTC to Rural households from ongoing scheme (MVS) including Distribution Strengthening
Contractor COCHIN MARINE INDUSTRIES (Mob: 9388961464)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 06/01/2022
Scheduled date of Completion as per agreement 30 Jun 2022
Expected date of Completion 31/12/2022

Processing Dates

TS Date 23 Oct 2020
Estimate Approval 23 Oct 2020
NIT Approval 12 Oct 2021
Tender Closing 06 Jan 2022
Technichal Pre-Qualification 06 Jan 2022
Price bid opening 06 Jan 2022

Approval Dates

Workorder Date 21 Dec 2021
NA 06 Jan 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Mathilakam AE
Date: 27/06/2024

Work in progress | 53% Completed

OUT OF 3067 FHTC, 1920 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-7650.97/9000m ,200 mm DI-558.5/623m, 250mm DI-2272.07/2529m,350mm DI-1672.1/1894m,300 mm DI -621/623m,400 mm DI-566.7/626 ,50 mm pvc-12183.50/13000,500mm DI - 26/159,pipe laying work is ongoing. 13th & part bill submitted. interconnection work and connection ongoing.

Attached images

img

Mathilakam AE
Date: 26/06/2024

Work in progress | 53% Completed

OUT OF 3067 FHTC, 1920 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-7650.97/9000m ,200 mm DI-558.5/623m, 250mm DI-2272.07/2529m,350mm DI-1672.1/1894m,300 mm DI -621/623m,400 mm DI-566.7/626 ,50 mm pvc-12183.50/13000,500mm DI - 26/159,pipe laying work is ongoing. 13th & part bill submitted. interconnection work and connection ongoing.