Project | JJM - Kaipamangalam Panchayath PHASE I-CWSS to Nattika Firka-Providing FHTC to Rural households from ongoing scheme (MVS) including Distribution Strengthening(3432 No FHTC) |
---|---|
Project Code | TCRJJM08205183P1 |
Type | Package |
Main Project | JJM - Kaipamangalam Panchayath PHASE I-CWSS to Nattika Firka-Providing FHTC to Rural households from ongoing scheme (MVS) including Distribution Strengthening |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM - Kaipamangalam Panchayath PHASE I-CWSS to Nattika Firka-Providing FHTC to Rural households from ongoing scheme (MVS) including Distribution Strengthening(3432 No FHTC) |
Status | On-going |
District | Thrissur |
Executing Office | Mathilakam PH Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 87000000 |
TS Number | TS/2020-2021/2020/20462 |
Technical specification | JJM - Kaipamangalam Panchayath PHASE I-CWSS to Nattika Firka-Providing FHTC to Rural households from ongoing scheme (MVS) including Distribution Strengthening |
Contractor | COCHIN MARINE INDUSTRIES (Mob: 9388961464) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 06/01/2022 |
---|---|
Scheduled date of Completion as per agreement | 30 Jun 2022 |
Expected date of Completion | 31/12/2022 |
TS Date | 23 Oct 2020 |
---|---|
Estimate Approval | 23 Oct 2020 |
NIT Approval | 12 Oct 2021 |
Tender Closing | 06 Jan 2022 |
Technichal Pre-Qualification | 06 Jan 2022 |
Price bid opening | 06 Jan 2022 |
Workorder Date | 21 Dec 2021 |
---|---|
NA | 06 Jan 2022 |
Mathilakam AE |
Date: 27/06/2024 |
Work in progress | 53% Completed
OUT OF 3067 FHTC, 1920 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-7650.97/9000m ,200 mm DI-558.5/623m, 250mm DI-2272.07/2529m,350mm DI-1672.1/1894m,300 mm DI -621/623m,400 mm DI-566.7/626 ,50 mm pvc-12183.50/13000,500mm DI - 26/159,pipe laying work is ongoing. 13th & part bill submitted. interconnection work and connection ongoing.
Attached images
Mathilakam AE |
Date: 26/06/2024 |
Work in progress | 53% Completed
OUT OF 3067 FHTC, 1920 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-7650.97/9000m ,200 mm DI-558.5/623m, 250mm DI-2272.07/2529m,350mm DI-1672.1/1894m,300 mm DI -621/623m,400 mm DI-566.7/626 ,50 mm pvc-12183.50/13000,500mm DI - 26/159,pipe laying work is ongoing. 13th & part bill submitted. interconnection work and connection ongoing.