AMRUT-"Providing FHTC to households in Thrissur Corporation Area
Project |
AMRUT-"Providing FHTC to households in Thrissur Corporation Area |
Project Code |
TCRAMRUT122213781 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
AMRUT-"Providing FHTC to households in Thrissur Corporation Area |
Status |
On-going |
District |
Thrissur |
Executing Office |
Thrissur PH Dn |
AS Amount (Rs) |
70000000
|
AS Number |
G.O.(Rt)No.3205/2022/LSGD |
TS Amount (Rs) |
10000000 |
TS Number |
WRD/KWA-CE(CR)/EST_TS/16528/2022_26_1_1 |
Total Bill Submitted (Rs) |
10000000 |
Total Bill Paid (Rs) |
10000000 |
Population Benefitted |
184 |
Capacity in MLD |
0.04 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Thrissur Corporation Area |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT-1.0-Providing FHTC's to households in Thrissur Corporation Area Package VIII-Supply and laying of Annular Corrugated Metallic flexible hose pipe in Floating Structure walk way -Pipeline Work |
Peechi PH Sn |
|
2 |
AMRUT-1-Providing FHTC to households in Thrissur Corporation Area-Package X - Additional work- Providing FHTCs (500Nos) and related pipeline works-Pipeline Work |
Thrissur WW Sn 1 |
|
3 |
AMRUT-1-Providing FHTC to households in Thrissur Corporation Area-Under Ollukkara zone, Thrissur Corporation (7 Crore Balance fund) Package 12-General Civil Work |
Thrissur WW Sn 1 |
|
4 |
AMRUT-"Providing FHTC to households in Thrissur Corporation Area"-Package I |
Thrissur WW Sn 1 |
|
5 |
AMRUT-"Providing FHTC to households in Thrissur Corporation Area"- Package II Pipeline Work |
Thrissur WW Sn 1 |
|
6 |
AMRUT-Providing FHTC to households in Thrissur Corporation Area -Package IV Pipeline Work |
Thrissur WW Sn 2 |
|
7 |
AMRUT-Providing FHTC to households in Thrissur Corporation Area - Package IX-Supply installation testing and commissioning two run of 400 sqm aluminium power cable from 1000KVA transformer room to floating panel room at Peechi -General Civil Work |
Peechi PH Sn |
|
8 |
AMRUT-Providing FHTC to households in Thrissur Corporation Area -Package V Pipeline Work |
Thrissur WW Sn 2 |
|
9 |
AMRUT-Providing FHTC to households in Thrissur Corporation Area -PACKAGE XI - Providing 350 FHTC in Koorkenchery and Ayyanthole area-Pipeline Work |
Thrissur WW Sn 2 |
|
10 |
AMRUT_Providing FHTC to households in Thrissur Corporation Area_Pipe line extensions along Caico Road (Package III) |
Thrissur WW Sn 1 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
02 Apr 2024 |
Work in progress. |
Thrissur PH Dn EE |
|
07 Mar 2024 |
Package I-79%-Total 525 connection tagging work in progress, Pipe laying completed -1650 m, Package II-100%-Work completed Package III-work completed. First part bill paid.Package X-10% -connection work in progress |
Thrissur WW Sn - AE 1 |
|
05 Mar 2024 |
Package I-79%-Total 525 connection tagging work in progress, Pipe laying completed -1650 m, Package II-100%-Work completed and 560 connection given out of 500 connection. One part bill paid. Second and final bill under preparation,Package III-95%-GSB completed. First part bill paid.Package X-1% -Site handover, work started |
Thrissur WW Sn - AE 1 |
|
04 Mar 2024 |
PKG-I,II & III -WORK IN PROGRESS |
Thrissur WW Sn - AE 1 |
|
29 Feb 2024 |
PKG-I,II & III -WORK IN PROGRESS |
Thrissur WW Sn - AE 1 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
17/04/2023 |
Scheduled date of Completion of the Project |
24 Nov 2023 |
Expected date of Completion |
31/05/2024 |
Processing Dates
AS Date |
26 Dec 2022 |
TS Date |
18 Mar 2023 |