WSS to Karadka, Kumbadaje and Delampdy

Project WSS to Karadka, Kumbadaje and Delampdy
Project Code KGDJJM052215871
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Supplying and Laying of Distribution system and Providing FHTC-Pipeline Work
Status On-going
District Kasaragod
Executing Office Kanhangad Project Division
AS Amount (Rs) 1756900000
AS Number GO (Rt) 401/2022/WRD
TS Amount (Rs) 833000000
TS Number WRD/KWA-CE(NR)/EST_TS/15260/2022_26_1_1
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted 17930
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 JAl Jeevan Mission (JJM)-JJM-KASARAGOD DISTRICT - WSS TO KARADUKKA ,KUMBADAJE AND DELAMPADI GRAMAPANCHAYATH - CONSTRUCTION OF INTAKE WELL CUM PUMP HOUSE , 10 MLD TREATMENT PLANT ,20 LL CAPACITY ,9.0LL CAPACITY OHSR AND ALIED STRUCTURES etc.-Pipeline Work Kanhangad Project Division
2 Jal Jeevan Mission (JJM)-WSS to Karadka, Kumbadaje and Delampdy-Supplying and Laying of Distribution system and Providing FHTC-Pipeline Work Kanhangad Project Division
3 WSS TO KARADKA,KUMBADAJE AND DELAMPADY PANCHAYATHS-CONSTRUCTION OF 2.5LL OHSR AT PANDY-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs Kanhangad Project Division

No status have been added to this project

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 01/10/2023
Scheduled date of Completion of the Project 30 Sep 2024
Expected date of Completion Date is not specified

Processing Dates

AS Date 13 May 2022
TS Date 16 Jul 2023

Other details