Improvement of water supply system for Guruvayur - Package II - Phase II

Project Improvement of water supply system for Guruvayur - Package II - Phase II
Project Code TCRGOI0917546P2
Type Package
Main Project AMRUT -2016-17,2017-18 WSS to Guruvayur Municipality in Thrissur District-Improvement of water supply system for Guruvayur - Package I & II (Revised AS -81.34Cr)
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description RWPM-500mm/600mm DI K9 & 630mm HDPE-38.987km
Status On-going
District Thrissur
Executing Office Nattika Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 605700000
TS Number TS/CE/CR/KWA/65/17-18
Technical specification RWPM-500mm/600mm DI K9 & 630mm HDPE-38.987km
Contractor J &B Engineering & construction company (Mob: 9447715266)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
01 Sep 2020 27 Dec 2021 Pending Road Cut Related Risk Permission for road cutting not obtained from PWD. Chavakkad Wadakkanchery road is a major road having heavy traffic. Multiple pipe lines of different works are to be laid combined in this road. Work restarted Solved

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 04/09/2018
Scheduled date of Completion as per agreement 03 Mar 2020
Expected date of Completion 31/08/2023

Processing Dates

TS Date 29 Jan 2018
Estimate Approval 29 Jan 2018
NIT Approval 29 Jun 2018
Tender Closing 10 May 2018
Technichal Pre-Qualification 29 May 2018
Price bid opening 04 Jun 2018

Approval Dates

Workorder Date 04 Sep 2018
NA 14 Feb 2018

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Nattika Project Dn
Date: 18/10/2023

Work has been completed | 100% Completed

Work completed..

Nattika Project Dn
Date: 17/10/2023

Work in progress | 97% Completed

RWPM-39 Km pipe laying completed. Pipe laying from Poovathur to Pavaratty , Koombuly bridge crossing and Chirakkal bridge crossing works are pending.