| Project | DEPOSIT-Pipeline extention at 34th mile-Pipeline extention at 34th mile-General Civil Work |
|---|---|
| Project Code | IDKDEPO082117646P1 |
| Type | Package |
| Main Project | DEPOSIT-Pipeline extention at 34th mile-Pipeline extention at 34th mile-General Civil Work |
| Funding Agency | DEPO |
| Category | Deposit Work |
| Type of scheme | Water Supply |
| Scheme | DEPO |
| Description | DEPOSIT-Pipeline extention at 34th mile-Pipeline extention at 34th mile-General Civil Work |
| Status | On-going |
| District | Idukki |
| Executing Office | Peerumedu Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 149797 |
| TS Number | 29923/2024-2023 |
| Technical specification | 32mm GI-200m |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 15/07/2025 |
|---|---|
| Scheduled date of Completion as per agreement | 15 Sep 2025 |
| Expected date of Completion | 15/09/2025 |
| TS Date | 22 Mar 2025 |
|---|---|
| Estimate Approval | 22 Mar 2025 |
| NIT Approval | 25 Mar 2025 |
| Tender Closing | 01 Apr 2025 |
| Technichal Pre-Qualification | 01 Apr 2025 |
| Price bid opening | 02 Apr 2025 |
| Workorder Date | 04 Jul 2025 |
|---|---|
| NA | 05 Jul 2025 |
| Peerumedu Sn AE |
| Date: 23/12/2025 |
Work has been completed | 100% Completed
Compleated.
| Peerumedu Sn AE |
| Date: 30/07/2025 |
Work has started | 0% Completed
Not started.