AMRUT 2.0- Attingal Municipality PHAS-Proposals for Improving the WaterSupply System In Attingal Muncipal Area Pipeline Work

Project AMRUT 2.0- Attingal Municipality PHAS-Proposals for Improving the WaterSupply System In Attingal Muncipal Area Pipeline Work
Project Code TVMAMRUT022314624P1
Type Package
Main Project AMRUT 2.0- Attingal Municipality PHASE -Proposals for Improving the WaterSupply System In Attingal Muncipal Area Pipeline Work
Funding Agency AMRUT
Category AMRUT 2
Type of scheme Water Supply
Scheme AMRUT
Description AMRUT 2.0- Attingal Municipality PHAS-Proposals for Improving the WaterSupply System In Attingal Muncipal Area Pipeline Work
Status On-going
District Thiruvananthapuram
Executing Office Attingal WS Sn 1
Agreement Number
Agreement Date
TS Amount (Rs) 54500000
TS Number 5.4 Cr, WRD/KWA-CE(SR)/EST_TS/2891/2022_26_1_1 Dated: 03-06-2023
Technical specification Pipe line extension and providing FHTCs

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 16/06/2023
Scheduled date of Completion as per agreement 02 Jan 2024
Expected date of Completion 30/11/2024

Processing Dates

TS Date 03 Jun 2023
Estimate Approval 03 Jun 2023
NIT Approval 03 Jun 2023
Tender Closing 19 Jun 2023
Price bid opening 19 Jun 2023

Approval Dates

Workorder Date 03 Jul 2023
NA 21 Jul 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Attingal WS Sn 1 - AE
Date: 25/09/2026

Work in progress | 99% Completed

restoration work ongoing.

Attingal WS Sn 1 - AE
Date: 22/09/2026

Work in progress | 99% Completed

restoration work ongoing.