Distribution main from Kakkakunnu OHSR to KCT Jn (250mm DI K9) - Connected to existing 200mm AC Pipe - in Sooranadu South Panchayath Distribution main from Kakkakunnu OHSR to Patharam HS Jn (250mm DI K9) - Connected to existing 200mm AC Pipe - in Sooranadu South Panchayath

Project Distribution main from Kakkakunnu OHSR to KCT Jn (250mm DI K9) - Connected to existing 200mm AC Pipe - in Sooranadu South Panchayath Distribution main from Kakkakunnu OHSR to Patharam HS Jn (250mm DI K9) - Connected to existing 200mm AC Pipe - in Sooranadu South Panchayath
Project Code KLMGOI1114485P2
Type Package
Main Project CENT.SPONSD ACCELERATED RWS SCHEME-PLAN(10)-ARWSS to West Kallada, Sooranad South and Sasthamcotta Pt. (1558)I
Funding Agency GOI
Category ARP Central
Type of scheme Water Supply
Scheme
Description Distribution main from Kakkakunnu OHSR to KCT Jn (250mm DI K9) - Connected to existing 200mm AC Pipe - in Sooranadu South Panchayath Distribution main from Kakkakunnu OHSR to Patharam HS Jn (250mm DI K9) - Connected to existing 200mm AC Pipe - in Sooranadu South Panchayath
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs)
TS Number
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 03/05/2019
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion Date is not specified

Processing Dates

AS Date 24 Nov 2014
TS Date 30 Jan 2015

Approval Dates

Workorder Date 10 Apr 2019
NA 03 May 2019

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project HD
Date: 24/06/2020

Work has been completed | 100% Completed

WORK COMPLETED.