Project | Jal Jeevan Mission- 2020-21- Phase I -Edathiruthy Grama Panchayath- Providing FHTC to Rural house holds by augmentation of existing schemes and by ongoing schemes (MVS) |
---|---|
Project Code | TCRJJM08205245P1 |
Type | Package |
Main Project | Jal Jeevan Mission- 2020-21- Phase I -Edathiruthy Grama Panchayath- Providing FHTC to Rural house holds by augmentation of existing schemes and by ongoing schemes (MVS) |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission- 2020-21- Phase I -Edathiruthy Grama Panchayath- Providing FHTC to Rural house holds by augmentation of existing schemes and by ongoing schemes (MVS) - 2300 nos |
Status | On-going |
District | Thrissur |
Executing Office | Vadanappalli Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 62900000 |
TS Number | TS/2020-2021/2020/21868 |
Technical specification | FHTC s 2500 nos. |
Contractor | THADATHIL MOHAMMED ALI (Mob: 9447733327) |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
10 Jun 2022 | Pending | Pending | Road Cut Related Risk | Application submitted toNH section for road cutting request .due to corrections they returned the application wuth adequate directions. | No comments available. | Pending |
24 Mar 2021 | Pending | Pending | Road Cut Related Risk | ROW/107029/10126 - crossing at chentrappinni center ROW/107029/10129 - chentrappinni center to south | No comments available. | Pending |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 22/10/2020 |
---|---|
Scheduled date of Completion as per agreement | 31 Mar 2021 |
Expected date of Completion | 31/03/2024 |
TS Date | 22 Oct 2020 |
---|---|
Estimate Approval | 22 Oct 2020 |
NIT Approval | 28 Oct 2020 |
Tender Closing | 09 Nov 2020 |
Technichal Pre-Qualification | 09 Nov 2020 |
Price bid opening | 09 Nov 2020 |
Workorder Date | 30 Dec 2020 |
---|---|
NA | 23 Mar 2021 |
Vadanappilly AE |
Date: 24/06/2024 |
Work in progress | 67% Completed
10 th and Part bill submitted. (1376 connections completed out of 2300 (801 HTCs and 575 FHTCs)..
Vadanappilly AE |
Date: 11/06/2024 |
Work in progress | 67% Completed
10 th and Part bill submitted. (1376 connections completed out of 2300 (801 HTCs and 575 FHTCs)..