Jal Jeevan Mission- 2020-21- Phase I -Edathiruthy Grama Panchayath- Providing FHTC to Rural house holds by augmentation of existing schemes and by ongoing schemes (MVS)

Project Jal Jeevan Mission- 2020-21- Phase I -Edathiruthy Grama Panchayath- Providing FHTC to Rural house holds by augmentation of existing schemes and by ongoing schemes (MVS)
Project Code TCRJJM08205245P1
Type Package
Main Project Jal Jeevan Mission- 2020-21- Phase I -Edathiruthy Grama Panchayath- Providing FHTC to Rural house holds by augmentation of existing schemes and by ongoing schemes (MVS)
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission- 2020-21- Phase I -Edathiruthy Grama Panchayath- Providing FHTC to Rural house holds by augmentation of existing schemes and by ongoing schemes (MVS) - 2300 nos
Status On-going
District Thrissur
Executing Office Vadanappalli Sn
Agreement Number
Agreement Date
TS Amount (Rs) 62900000
TS Number TS/2020-2021/2020/21868
Technical specification FHTC s 2500 nos.
Contractor THADATHIL MOHAMMED ALI (Mob: 9447733327)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
10 Jun 2022 Pending Pending Road Cut Related Risk Application submitted toNH section for road cutting request .due to corrections they returned the application wuth adequate directions. No comments available. Pending
24 Mar 2021 Pending Pending Road Cut Related Risk ROW/107029/10126 - crossing at chentrappinni center ROW/107029/10129 - chentrappinni center to south No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 22/10/2020
Scheduled date of Completion as per agreement 31 Mar 2021
Expected date of Completion 31/03/2024

Processing Dates

TS Date 22 Oct 2020
Estimate Approval 22 Oct 2020
NIT Approval 28 Oct 2020
Tender Closing 09 Nov 2020
Technichal Pre-Qualification 09 Nov 2020
Price bid opening 09 Nov 2020

Approval Dates

Workorder Date 30 Dec 2020
NA 23 Mar 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Vadanappilly AE
Date: 24/06/2024

Work in progress | 67% Completed

10 th and Part bill submitted. (1376 connections completed out of 2300 (801 HTCs and 575 FHTCs)..

Vadanappilly AE
Date: 11/06/2024

Work in progress | 67% Completed

10 th and Part bill submitted. (1376 connections completed out of 2300 (801 HTCs and 575 FHTCs)..