JJM 2020 -21 -Supplying, laying, testing, commissioning and mace of distribution system and providing FHTCs (4565nos) and supply & erection of VT pumpset for raw water pumping main in Pattithara Panchayath- Phase II
Project |
JJM 2020 -21 -Supplying, laying, testing, commissioning and mace of distribution system and providing FHTCs (4565nos) and supply & erection of VT pumpset for raw water pumping main in Pattithara Panchayath- Phase II |
Project Code |
PKDJJM09219397 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM 2020 -21 -Supplying, laying, testing, commissioning and mace of distribution system and providing FHTCs (4565nos) and supply & erection of VT pumpset for raw water pumping main in Pattithara Panchayath- Phase II |
Status |
On-going |
District |
Palakkad |
Executing Office |
Shornur PH Dn |
AS Amount (Rs) |
227200000
|
AS Number |
G.O.(Rt)No.489/2021/WRD |
TS Amount (Rs) |
164500000 |
TS Number |
TS/2021-2022/2021/278 |
Total Bill Submitted (Rs) |
104541021 |
Total Bill Paid (Rs) |
104541021 |
Population Benefitted |
33157 |
Capacity in MLD |
8.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
4565nos |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM 2020 -21 -Supplying, laying, testing, commissioning and mace of distribution system and providing FHTCs (4565nos) and supply & erection of VT pumpset for raw water pumping main in Pattithara Panchayath- Phase II |
Shoranur Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
12 Jun 2024 |
Work Completed.Prepairing Bill.
|
Shoranur PH Sn AE |
|
09 Jun 2024 |
Work Completed.Prepairing Bill. |
Shoranur PH Sn AE |
|
06 Jun 2024 |
Work Completed.Prepairing Bill
|
Shoranur PH Sn AE |
|
02 Jun 2024 |
Work Completed.Prepairing Bill |
Shoranur PH Sn AE |
|
26 May 2024 |
Work Completed.Prepairing Bill |
Shoranur PH Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
02/03/2022 |
Scheduled date of Completion of the Project |
01 Sep 2022 |
Expected date of Completion |
31/01/2024 |
Processing Dates
AS Date |
18 Sep 2021 |
TS Date |
25 Nov 2021 |