Project | JJM -2021-24 "Kuttichal and Poovachal panchayaths-"CWSS to Manoorkara Veeranakavu and Perumkulam villages "Phase II - Package V |
---|---|
Project Code | TVMJJM092110809P5 |
Type | Package |
Main Project | JJM 2021 2024 KUTTICHAL AND POOVACHAL PANCHAYATHS CWSS TO MANOORKARA VEERANAKAVU AND PERUMKULAM VILLAGES PHASE II |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Distribution network from Panniyode OHSR and providing Functional Household Tap Connections ( Fhtc No: 2660) in Poovachal Grama Panchayath |
Status | On-going |
District | Thiruvananthapuram |
Executing Office | Trivandrum Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 98380000 |
TS Number | TS/2021-2022/2021/43242 |
Technical specification | Distribution network from Panniyode OHSR and providing Functional Household Tap Connections ( Fhtc No: 2660) in Poovachal Grama Panchayath |
Contractor | Sri. Suraj. R (Mob: 9605883360) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 21/10/2022 |
---|---|
Scheduled date of Completion as per agreement | 09 Mar 2023 |
Expected date of Completion | 31/07/2023 |
TS Date | 22 Dec 2021 |
---|---|
Estimate Approval | 22 Dec 2021 |
NIT Approval | 07 Mar 2022 |
Tender Closing | 30 Mar 2022 |
Technichal Pre-Qualification | 19 Apr 2022 |
Price bid opening | 18 Jul 2022 |
Workorder Date | 10 Aug 2022 |
---|---|
NA | 29 Aug 2022 |
Thiruvananthapuram Project AE4 |
Date: 13/02/2024 |
Work has been completed | 100% Completed
maximum possible connection given and work completed.
Thiruvananthapuram Project AE4 |
Date: 05/11/2023 |
Work in progress | 88% Completed
No work in progress.