Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM-2020-21-WSS TO KERALASSERI PANCHAYATH IN PALAKKADDISTRICT – Phase II - Providing Distribution System and FHTCs IN PALAKKAD DISTRICT

Project JJM-2020-21-WSS TO KERALASSERI PANCHAYATH IN PALAKKADDISTRICT – Phase II - Providing Distribution System and FHTCs IN PALAKKAD DISTRICT
Project Code PKDJJM09203337
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JAL JEEVAN MISSION- 2020-21- WSS to Keralassery panchayaths-,supplying, laying, testing, commissioning and maintenance of distribution systems with providing FHTCs – 4140 Nos
Status On-going
District Palakkad
Executing Office Palakkad Project Dn
AS Amount (Rs) 214800000
AS Number G.O.(Rt)No.777/2020/WRD
TS Amount (Rs) 207107000
TS Number TS/2020-2021/2020/27943
Total Bill Submitted (Rs) 58582922
Total Bill Paid (Rs)
Population Benefitted 17598
Capacity in MLD 10.00
Actual Project Completion Date 31 Dec 2024
Coverage Keralasseri Grama Panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM-2020-21- WSS TO KERALASSERI PANCHAYATH IN PALAKKADDISTRICT – Phase II - Providing Distribution System and FHTCs IN PALAKKAD DISTRICT Project Division Palakkad

Overall Project Status

Status Date Overall Project Status Project Officer Contact
22 Jun 2024 82.775/143.831 km laying completed. Remaining PVC, GI & HDPE pipe laying progressing. PWD road cutting applied , permission to be obtained. Connection work not started. Palakkad Proj Dn AE 4
20 Jun 2024 82.775/143.831 km laying completed. Remaining PVC, GI & HDPE pipe laying progressing. PWD road cutting applied , permission to be obtained. Connection work not started. Palakkad Proj Dn AE 4
18 Jun 2024 82.775/143.831 km laying completed. Remaining PVC, GI & HDPE pipe laying progressing. PWD road cutting applied , permission to be obtained. Connection work not started. Palakkad Proj Dn AE 4
14 Jun 2024 82.225/143.831 km laying completed. Remaining PVC, GI & HDPE pipe laying progressing. PWD road cutting applied , permission to be obtained. Connection work not started. Palakkad Proj Dn AE 4
13 Jun 2024 80.723/143.831 km laying completed. Remaining PVC, GI & HDPE pipe laying progressing. PWD road cutting applied , permission to be obtained. Connection work not started. Palakkad Proj Dn AE 4

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 01/08/2023
Scheduled date of Completion of the Project 28 May 2024
Expected date of Completion 31/12/2024

Processing Dates

AS Date 18 Sep 2020
TS Date 05 Jan 2021

Other details

Project Officers View