Project | Jal Jeevan Mission (JJM)-Jal Jeevan Mission 2021-22 -Phase II - WSS to Kadappuram Panchayath- Construction of OHSR, Clear Water Pumping Main, Providing Distribution Network and FHTC to Kadappuram Panchayath-Construction of 10 LL OHSR and Construction of Compound Wall at Kadappuram -General Civil Work-1 |
---|---|
Project Code | TCRJJM022213952P2 |
Type | Package |
Main Project | Jal Jeevan Mission JJM 2021-2022 Phase II WSS to Kadappuram Panchayath- Construction of OHSR- CWPM -Providing Distribution Network and FHTC to Kadappuram Panchayath-Providing Distribution Network and road restoration work and FHTC to Kadappuram panchayath |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission (JJM)-Jal Jeevan Mission 2021-22 -Phase II - WSS to Kadappuram Panchayath- Construction of OHSR, Clear Water Pumping Main, Providing Distribution Network and FHTC to Kadappuram Panchayath-Construction of 10 LL OHSR and Construction of Compound Wall at Kadappuram -General Civil Work-1 |
Status | On-going |
District | Thrissur |
Executing Office | Nattika Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 54000000 |
TS Number | 6781/2023-2024 |
Technical specification | Construction of 10 LL OHSR and Construction of Compound Wall at Kadappuram |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 21/09/2023 |
---|---|
Scheduled date of Completion as per agreement | 20 Sep 2024 |
Expected date of Completion | 01/03/2024 |
TS Date | 20 Jun 2023 |
---|---|
Estimate Approval | 20 Jun 2023 |
Tender Closing | 27 Jul 2023 |
Price bid opening | 29 Jul 2023 |
Workorder Date | 21 Sep 2023 |
---|---|
NA | 07 Oct 2023 |
Nattika Project Dn AE 2 |
Date: 27/06/2024 |
Work in progress | 1% Completed
Boring of P1C3 pile ongoing..
Nattika Project Dn AE 2 |
Date: 26/06/2024 |
Work in progress | 1% Completed
Boring of pile P2D3 pile is completed. Hardrock found at 35.5m and it is drilled to .6m and the total length of 36.1m is achieved. Reinforcement cage inserted . Concreting of P2D3 pile completed at 8pm with third party inspection..