JJM- Kasargod district-Kinanur- Karinthalam Grama panchayath-Laying distribution system and providing FHTCs-JJM- Kasargod district-Kinanur- Karinthalam Grama panchayath-Laying distribution system and providing FHTCs- ZOne 3 & 4-Pipeline Work

Project JJM- Kasargod district-Kinanur- Karinthalam Grama panchayath-Laying distribution system and providing FHTCs-JJM- Kasargod district-Kinanur- Karinthalam Grama panchayath-Laying distribution system and providing FHTCs- ZOne 3 & 4-Pipeline Work
Project Code KGDJJM052215713
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM- Kasargod district-Kinanur- Karinthalam Grama panchayath-Laying distribution system and providing FHTCs-JJM- Kasargod district-Kinanur- Karinthalam Grama panchayath-Laying distribution system and providing FHTCs- ZOne 3 & 4-Pipeline Work
Status On-going
District Kasaragod
Executing Office Kanhangad Project Division
AS Amount (Rs) 946900000
AS Number GO (Rt.) No. 401/2022/WRD
TS Amount (Rs) 107800000
TS Number WRD/KWA-CE(NR)/EST_TS/6240/2022_26_3_2 Dated: 23-11-2022
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 JJM- Kasargod district-Kinanur- Karinthalam Grama panchayath-Laying distribution system and providing FHTCs-JJM- Kasargod district-Kinanur- Karinthalam Grama panchayath-Laying distribution system and providing FHTCs- ZOne 3 & 4-Pipeline Work Kanhangad Project Division

Overall Project Status

Status Date Overall Project Status Project Officer Contact
21 Jun 2024 Work in progress. 3.5 km of pipeline laid Kanhangad Proj Dn AE - 2
19 Jun 2024 Work in progress. 3.5 km of pipeline laid Kanhangad Proj Dn AE - 2
17 Jun 2024 Work in progress. 3.5 km of pipeline laid Kanhangad Proj Dn AE - 2
14 Jun 2024 Work in progress. 3.5 km of pipeline laid Kanhangad Proj Dn AE - 2
12 Jun 2024 Work in progress. 3.5 km of pipeline laid Kanhangad Proj Dn AE - 2

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 10/10/2024
Scheduled date of Completion of the Project 09 Oct 2025
Expected date of Completion Date is not specified

Processing Dates

AS Date 13 May 2022
TS Date 23 Nov 2022

Other details

Project Officers View