JJM -Providing FHTC to All House holds of Muttom and Karimkunnam Panchayath in Idukki District and Extension of Distribution lines

Project JJM -Providing FHTC to All House holds of Muttom and Karimkunnam Panchayath in Idukki District and Extension of Distribution lines
Project Code IDKJJM08208412
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Providing FHTC to All House holds of Muttom and Karimkunnam Panchayath in Idukki District and Extension of Distribution lines in uncovered areas of Muttom and Karimkunnam Panchayaths
Status On-going
District Idukki
Executing Office Kattappana Project Dn
AS Amount (Rs) 1345100000
AS Number G.R(Rt) No. 541/2020/WRD
TS Amount (Rs) 254000000
TS Number TS/2021-2022/2020/4545
Total Bill Submitted (Rs) 101610080
Total Bill Paid (Rs) 101610080
Population Benefitted 14988
Capacity in MLD 11.00
Actual Project Completion Date Date is not specified
Coverage Muttom and Karimkunnam Panchayath

Packages

No. Project Name Location View
1 JJM -Providing FHTC to All House holds of Muttom and Karimkunnam Panchayath in Idukki District and Extension of Distribution lines Project Division Kattapana
2 JJM - WSS to Muttom & Karimkunnam Panchayaths in Idukki District.-Laying Clear water Pumping mains, Gravity mains and Construction of Reservoirs Project Division Kattapana
3 JJM - WSS to Muttom & Karimkunnam Panchayaths in Idukki District.- Supplying and laying of RWPM ,CWPM & distribution lines in various zones, Construction of various GLSRs & Supply and erection of RW & CW pumpsets Project Division Kattapana

Overall Project Status

Status Date Overall Project Status Project Officer Contact
18 May 2024 Package -1 -Work in progress ,Package -2-450mm, 300 mm , 250mm DI pipe laying work at malankara park , Package -3 Work order given to J.P Sajimon Kattapana Project Dn AE4
15 May 2024 Package -1 -Work in progress ,Package -2- Work in progress , Package -3 Work order given to J.P Sajimon Kattapana Project Dn AE4
12 May 2024 Package -1 -Work in progress ,Package -2- Work in progress , Package -3 Work order given to J.P Sajimon Kattapana Project Dn AE4
09 May 2024 Package -1 -Work in progress ,Package -2- 450 mm,300 mm and 250 mm DI pipe laying at malankara park, Package -3 Work order given to J.P Sajimon Kattapana Project Dn AE4
06 May 2024 Package -1 -Work in progress ,Package -2- replanting plants for laying 450 mm,300 mm and 250 mm DI at malankara park, Package -3 Work order given to J.P Sajimon Kattapana Project Dn AE4

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 22/06/2022
Scheduled date of Completion of the Project 30 Apr 2024
Expected date of Completion 31/03/2025

Processing Dates

AS Date 21 Aug 2020
TS Date 19 Nov 2021