Jal Jeevan Mission 2021-22:-3rd SLSSC –Puramattom Grama Panchayath (Final Phase) - Laying of Pipe Lines & Providing 2489 FHTC`s in Puramattom Panchayath

Project Jal Jeevan Mission 2021-22:-3rd SLSSC –Puramattom Grama Panchayath (Final Phase) - Laying of Pipe Lines & Providing 2489 FHTC`s in Puramattom Panchayath
Project Code PTAJJM092114884
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission 2021-22:-3rd SLSSC –Puramattom Grama Panchayath (Final Phase) - Laying of Pipe Lines & Providing 2489 FHTC`s in Puramattom Panchayath
Status On-going
District Pathanamthitta
Executing Office Thiruvalla PH Dn
AS Amount (Rs) 242600000
AS Number GO(Rt)No.489/2021/WRD
TS Amount (Rs) 186700000
TS Number WRD/KWA-CE(SR)/EST_TS/8557/2022_26_1_1
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 9960
Capacity in MLD 0.99
Actual Project Completion Date Date is not specified
Coverage Laying of pipe lines and providing

Packages

No. Project Name Location View
1 Jal Jeevan Mission 2021-22:-3rd SLSSC –Puramattom Grama Panchayath (Final Phase) - Laying of Pipe Lines & Providing 2489 FHTC`s in Puramattom Panchayath Pullad Section

Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Jun 2024 32000 M of PVC Pipes Laid. 611 FHTCs Provided & Geo Tagged Pullad PH Sn - AE
21 Jun 2024 32000 M of PVC Pipes Laid. 611 FHTCs Provided & Geo Tagged Pullad PH Sn - AE
18 Jun 2024 32000 M of PVC Pipes Laid. 611 FHTCs Provided & Geo Tagged. 590 Connections IMIS done. Pullad PH Sn - AE
13 Jun 2024 32000 M of PVC Pipes Laid. 611 FHTCs Provided & Geo Tagged. 590 Connections IMIS done. Pullad PH Sn - AE
11 Jun 2024 32000 M of PVC Pipes Laid. 611 FHTCs Provided & Geo Tagged. Pullad PH Sn - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 18/09/2021
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion Date is not specified

Processing Dates

AS Date 18 Sep 2021
TS Date 30 Jun 2023

Other details

Project Officers View