- Home
- Jal Jeevan Mission (JJM)- Alappuzha Dist...
Jal Jeevan Mission (JJM)- Alappuzha District - Providing Functional House hold Tap Connections (FHTC) in Thuravoor Panchayath and allied works (2352 FHTC's)
Project |
Jal Jeevan Mission (JJM)- Alappuzha District - Providing Functional House hold Tap Connections (FHTC) in Thuravoor Panchayath and allied works (2352 FHTC's) |
Project Code |
ALPJJM08204194 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission (JJM)- Alappuzha District - Providing Functional House hold Tap Connections (FHTC) in Thuravoor Panchayath and allied works (2352 FHTC's) |
Status |
On-going |
District |
Alappuzha |
Executing Office |
Alappuzha PH Dn |
AS Amount (Rs) |
31600000
|
AS Number |
GO(Rt0No.541/2020/WRD |
TS Amount (Rs) |
31300000 |
TS Number |
6432/2020-2021 |
Total Bill Submitted (Rs) |
14181274 |
Total Bill Paid (Rs) |
10105130 |
Population Benefitted |
9500 |
Capacity in MLD |
107.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Thuravoor panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM)- Alappuzha District - Providing Functional House hold Tap Connections (FHTC) in Thuravoor Panchayath and allied works |
Thuravur PH Sn |
|
2 |
Jaljeevan Mission (JJM)- Alappuzha District- Providing functional household tap connections FHTCs in Thuravoor Grama Panchayaths and allied work – Balance work for extending distribution line. |
Thuravur PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
13 Jun 2022 |
Package 1 - 99 % and package 2- completed |
Cherthala PH SUb Dn |
|
03 Jun 2022 |
Package 1 - 99 % and package 2- completed |
Cherthala PH SUb Dn |
|
02 Jun 2022 |
Package 1 - 99 % and package 2- completed |
Cherthala PH SUb Dn |
|
01 Jun 2022 |
Package 1 - 99 % and package 2- completed |
Cherthala PH SUb Dn |
|
31 May 2022 |
Package 1 - 99 % and package 2- completed |
Cherthala PH SUb Dn |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
08/10/2020 |
Scheduled date of Completion of the Project |
02 May 2021 |
Expected date of Completion |
31/08/2022 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
27 Aug 2020 |