KIIFB-Augmentation and Modernization of WSS to Alappuzha Municipality, Aryad, Mannanchery and Mararikulam South Panchayaths Package I
Project |
KIIFB-Augmentation and Modernization of WSS to Alappuzha Municipality, Aryad, Mannanchery and Mararikulam South Panchayaths Package I |
Project Code |
ALPKIIFB0619496P2 |
Type |
Package |
Main Project |
KIIFB-Augmentation and Modernization of WSS to Alappuzha Municipality, Aryad, Mannanchery and Mararikulam South Panchayaths
|
Funding Agency |
KIIFB |
Category |
KIIFB WATER SUPPLY SCHEME |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
Construction of 16 LL OHSR and 5 LL Sump at Chathanad in Alappuzha Municiplaity Construction of 16 LL OHSR and 3 LL Sump at Vadikadu in Alappuzha Municiplaity Construction of 12 LL OHSR and 3 LL Sump cum pump house at Kattoor in Mararikulam South Pt Construction of Operator Quarters Laying clear Water Pumping main Kulamakki to OHSR (R20) at FHC Kattoor – 280mm HDPE - 2600M Railway crossing works Supplying and fixing clear water pump sets 30 HP 2 Nos,25HP 2 Nos,20 HP 2 Nos ,10 HP 2 Nos |
Status |
On-going |
District |
Alappuzha |
Executing Office |
KIIFB Projects (ALP) |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
207700000 |
TS Number |
TS/2020-2021/2020/2802 |
Technical specification |
Construction of 16 LL OHSR and 5 LL Sump at Chathanad in Alappuzha Municiplaity Construction of 16 LL OHSR and 3 LL Sump at Vadikadu in Alappuzha Municiplaity Construction of 12 LL OHSR and 3 LL Sump cum pump house at Kattoor in Mararikulam South Pt Construction of Operator Quarters Laying clear Water Pumping main Kulamakki to OHSR (R20) at FHC Kattoor – 280mm HDPE - 2600M Railway crossing works Supplying and fixing clear water pump sets 30 HP 2 Nos,25HP 2 Nos,20 HP 2 Nos ,10 HP 2 Nos |
Contractor |
M/s Midland Engineering and contracting company (Mob: 6282209419) |
No project review have been added to this project
Reported Issues
Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
25 Oct 2021 |
Pending |
Pending |
Contract Related Risks |
Push through between Kalavoor and Tumboli stations at sarvodayapuram in Mararikulam south Panchayat at Chainage between 49/100-49/200.Joint inspection conducted on 7/9/2021 |
No comments available. |
Pending |
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
26/02/2021 |
Scheduled date of Completion as per agreement |
25 Feb 2023 |
Expected date of Completion |
25/11/2023 |
Processing Dates
TS Date |
12 Nov 2020 |
Estimate Approval |
12 Nov 2020 |
NIT Approval |
13 Nov 2020 |
Tender Closing |
28 Nov 2020 |
Technichal Pre-Qualification |
24 Dec 2020 |
Price bid opening |
01 Dec 2020 |
Approval Dates
Workorder Date |
12 Feb 2021 |
NA |
26 Feb 2021 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Alappuzha KIIFB - AE 4 |
Date: 17/05/2024 |
Work in progress | 90% Completed
90% work completed. Time of completion extended up to 25.11.2023.Construction of 12LL OHSR at KATTOOR in Mararilkulam South Panchayat -Finishing Works. Construction of 16LL OHSR at VADIKADU-.Finishing Works. KSEB Power connection obtained and trial running conducted for pump erected at GLSR Vadikad. Construction of 16LL OHSR at CHATHANAD - Bottom slab concreting work completed. Haunch concreting work completed. Column Inside tank concreting work completed. Masonry work started .Side wall Third lift concreting work completed . Shuttering and reinforcement work for roof slab is completed. Roof slab concreting completed. OHSR inside and outside plastering work going on. Column pipe work going on. Laying of clear water pumping main from Kulamakki to Kattoor OHSR - 2580.30 mtrs(Total 2800 mtrs).Balance laying work progressing Replacing of motor (2nos )& MS work at Kulamakki pumphouse is completed . PWD Road cutting permission was obtained on 05-04-2023. Work along PWD road was about completed. CF Pump sets Supplied and erected 2 nos at Vadikadu OHSR. Construction of Operator Quarters- Floor tile work started. Finishing works going on..
Alappuzha KIIFB - AE 4 |
Date: 16/05/2024 |
Work in progress | 90% Completed
90% work completed. Time of completion extended up to 25.11.2023.Construction of 12LL OHSR at KATTOOR in Mararilkulam South Panchayat -Finishing Works. Construction of 16LL OHSR at VADIKADU-.Finishing Works. KSEB Power connection obtained and trial running conducted for pump erected at GLSR Vadikad. Construction of 16LL OHSR at CHATHANAD - Bottom slab concreting work completed. Haunch concreting work completed. Column Inside tank concreting work completed. Masonry work started .Side wall Third lift concreting work completed . Shuttering and reinforcement work for roof slab is completed. Roof slab concreting completed. OHSR inside and outside plastering work going on. Column pipe work going on. Laying of clear water pumping main from Kulamakki to Kattoor OHSR - 2580.30 mtrs(Total 2800 mtrs).Balance laying work progressing Replacing of motor (2nos )& MS work at Kulamakki pumphouse is completed . PWD Road cutting permission was obtained on 05-04-2023. Work along PWD road was about completed. CF Pump sets Supplied and erected 2 nos at Vadikadu OHSR. Construction of Operator Quarters- Floor tile work started. Finishing works going on..