Project | Jal Jeevan Mission (JJM)-2020-2021 Phase I & II-Providing FHTC by retrofitting/extension and augmentation of ongoing water supply scheme in Balusseri Grama Panchayath-Providing online boosting stations and FHTC in Ward No-3 and 4 |
---|---|
Project Code | CLTJJM092115581P5 |
Type | Package |
Main Project | Jal Jeevan Mission (JJM)-2020-2021 Phase I & II-Providing FHTC by retrofitting/extension and augmentation of ongoing water supply scheme in Balusseri Grama Panchayath-Providing online boosting station and FHTC's |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission (JJM)-2020-2021 Phase I & II-Providing FHTC by retrofitting/extension and augmentation of ongoing water supply scheme in Balusseri Grama Panchayath-Providing online boosting stations and FHTC in Ward No-3 and 4-Pipeline Work-1-at Njattippara and Parakkuzhi |
Status | On-going |
District | Kozhikkode |
Executing Office | Koyilandy PH Sn 1 |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 2270000 |
TS Number | 3308/23_26_5_4 |
Technical specification |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 22/11/2023 |
---|---|
Scheduled date of Completion as per agreement | Date is not specified |
Expected date of Completion | 31/03/2024 |
TS Date | 29 Sep 2023 |
---|---|
Estimate Approval | 27 Feb 2023 |
Tender Closing | 12 Oct 2023 |
Price bid opening | 13 Oct 2023 |
Koyilandy PH Section 1 - AE |
Date: 25/06/2024 |
Work in progress | 80% Completed
All works completed except Pump set and power connection..
Koyilandy PH Section 1 - AE |
Date: 19/06/2024 |
Work in progress | 80% Completed
All works completed except Pump set and power connection..