Jal Jeevan Mission- Aloor Grama Panchayath (Appendix 1) -Providing FHTC and Retrofitting/Augmentation of Existing Rural Water Supply Schemes

Project Jal Jeevan Mission- Aloor Grama Panchayath (Appendix 1) -Providing FHTC and Retrofitting/Augmentation of Existing Rural Water Supply Schemes
Project Code TCRJJM07203798
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission- Aloor Grama Panchayath (Appendix 1) -Providing FHTC and Retrofitting/Augmentation of Existing Rural Water Supply Schemes
Status On-going
District Thrissur
Executing Office Chalakkudy PH Sn
AS Amount (Rs) 43000000
AS Number GO(Rt) No.541/2020/WRD
TS Amount (Rs) 43000000
TS Number TS/2020-2021/2020/14323
Total Bill Submitted (Rs) 38754813
Total Bill Paid (Rs) 38754813
Population Benefitted 25000
Capacity in MLD 1.80
Actual Project Completion Date 21 May 2024
Coverage 60% of Aloor Panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission - 2020-21- Providing water service connection various Schools and Anganwadies in Aloor Grama Panchayath under WSP Section No.I Chalakudy Mathilakam PH Sn
2 Jal Jeevan Mission - 2020-21- Supply and installation of Water purifier with Multiple purification by UV process Filteration unit to Balance Schools in Aloor Grama Panchayaths under WSP Section No.I Chalakudy Chalakkudy PH Sn
3 Jal Jeevan Mission - 2020-21- Supply and installation of Water purifier with Multiple purification by UV process Filteration unit to various Anganwadies in Aloor Grama Panchayath under WSP Section No.I Chalakudy Chalakkudy PH Sn
4 Jal Jeevan Mission - 2020 - 21 - Supply and installation of Water purifier with Multiple purification by UV process Filteration unit to various Schoolsin Aloor GP under WSP Section No.I Chalakudy Chalakkudy PH Sn
5 Jal Jeevan Mission- Aloor Grama Panchayath (Appendix 1) -Providing FHTC and Retrofitting/Augmentation of Existing Rural Water Supply Schemes- 1950 FHTC Chalakkudy PH Sn
6 JJM-Aloor Gramapanchayath-Phase-1 balance work-Replacing damaged distribution lines-Pipe line work Chalakkudy PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
18 Mar 2023 Bill submitted to division Chalakudy AEE
10 Jan 2023 work completed Chalakudy AE 1
06 Jan 2023 1952 connections given Chalakudy AE 1
04 Jan 2023 1952 connections given Chalakudy AE 1
29 Dec 2022 1952 connections given Chalakudy AE 1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 17/06/2020
Scheduled date of Completion of the Project 08 May 2021
Expected date of Completion 21/05/2024

Processing Dates

AS Date 21 Aug 2020
TS Date 05 Sep 2020

Other details

Project Officers View