| Project | NABARD - WSS to Kottiyoor, Kelakam and Kanichar panchayaths in Iritty Taluk of Kannur District - Phase I - Package I |
|---|---|
| Project Code | KNRNABARD12173151P1 |
| Type | Package |
| Main Project | NABARD -RIDF-XXIII- WSS to Kottiyoor, Kelakam and Kanichar Panchayaths in Iritty Taluk of Kannur District - Phase I |
| Funding Agency | NABARD |
| Category | NABARD |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-98 (01) |
| Description | Construction of 8 m dia intake well cum pump house at Kalikayam in Bavali river, pumping main - 400 mm DI K9 - 850 m, 11 MLD WTP at Athithattu, |
| Status | On-going |
| District | Kannur |
| Executing Office | Koothuparamba Project Sn No2 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 102400000 |
| TS Number | TS/2018-19/2018/9685 |
| Technical specification | Construction of 8 m dia intake well cum pump house at Kalikayam in Bavali river, pumping main - 400 mm DI K9 - 850 m, 11 MLD WTP at Athithattu, |
| Contractor | KANNAN.K (Mob: 9447075396) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 01/03/2020 |
|---|---|
| Scheduled date of Completion as per agreement | 25 May 2020 |
| Expected date of Completion | 31/03/2022 |
| TS Date | 23 Aug 2018 |
|---|---|
| Estimate Approval | 23 Aug 2018 |
| NIT Approval | 13 Sep 2018 |
| Tender Closing | 20 Oct 2018 |
| Technichal Pre-Qualification | 23 Nov 2018 |
| Price bid opening | 23 Nov 2018 |
| Workorder Date | 26 Feb 2019 |
|---|---|
| NA | 27 Feb 2019 |
| Koothuparamba Proj AE 2 |
| Date: 22/10/2024 |
| Koothuparamba Proj AE 2 |
| Date: 07/06/2024 |
Work has been completed | 100% Completed
Commisioned at 20/5/2024.