MCS -Deposit work -Dismantling and removing the damaged and chocked 63mm dia waste line of the Microbiology lab of Blood bank building and allied works-MCS -Deposit work -Dismantling and removing the damaged and chocked 63mm dia waste line of the Microbiology lab of Blood bank building and allied works

Project MCS -Deposit work -Dismantling and removing the damaged and chocked 63mm dia waste line of the Microbiology lab of Blood bank building and allied works-MCS -Deposit work -Dismantling and removing the damaged and chocked 63mm dia waste line of the Microbiology lab of Blood bank building and allied works
Project Code TVMDEPO082213727P6
Type Package
Main Project Deposit Work-2022-23-KWA Medical college
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description MCS -Deposit work -Dismantling and removing the damaged and chocked 63mm dia waste line of the Microbiology lab of Blood bank building and allied works-MCS -Deposit work -Dismantling and removing the damaged and chocked 63mm dia waste line of the Microbiology lab of Blood bank building and allied works
Status On-going
District Thiruvananthapuram
Executing Office TVM Medical College Sn
Agreement Number
Agreement Date
TS Amount (Rs) 133300
TS Number 1472/2023
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 01/03/2023
Scheduled date of Completion as per agreement 15 Jun 2023
Expected date of Completion 03/06/2023

Processing Dates

TS Date 21 Feb 2023
Estimate Approval 21 Feb 2023
NIT Approval 21 Feb 2023
Tender Closing 09 Mar 2023
Technichal Pre-Qualification 09 Mar 2023
Price bid opening 13 Mar 2023

Approval Dates

Workorder Date 16 Mar 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Thiruvananthapuram - Med col - AE
Date: 01/09/2023

Work has been completed | 100% Completed

Work Completed.

Thiruvananthapuram - Med col - AE
Date: 16/08/2023

Work has been completed | 100% Completed

Work Completed.