- Home
- JJM-WSS to Paingottoor Panchayath in Ern...
JJM-WSS to Paingottoor Panchayath in Ernakulam District
Project |
JJM-WSS to Paingottoor Panchayath in Ernakulam District |
Project Code |
EKMJJM092110912 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
There are 1580 domestic water connections existing in the project area. It is assessed that
there are 4571 number of households in this area. Hence 2991 new water supply connections
have to be provided for attaining 100 % water supply at every households. Also the existing
connections have to be shifted to the new network. |
Status |
On-going |
District |
Ernakulam |
Executing Office |
Perumbavoor Project Dn |
AS Amount (Rs) |
172400000
|
AS Number |
G.O.(Rt)No.489/2021/WRD |
TS Amount (Rs) |
172400000 |
TS Number |
TS/2021-2022/2021/11673 Dated: 07-12-2021 |
Total Bill Submitted (Rs) |
25278109 |
Total Bill Paid (Rs) |
25278109 |
Population Benefitted |
15336 |
Capacity in MLD |
4.00 |
Actual Project Completion Date |
30 Mar 2023 |
Coverage |
Paingottoor panchayath in Ernakulam district |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
WSS to Paingottoor Panchayath in Ernakulam District |
Project Division Piravom(Kattapana) |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
02 Nov 2023 |
Providing FHTC are in progress. Distribution lines gap filling work in progress. |
Piravam Project Sub Dn AE 2 |
|
07 Sep 2023 |
Work is under good progress.Pipe laying through Kaliyar Kakkadassery KSTP road completed.Laying of distribution lines through panchayath roads in good progress.Interconnection works of already laid lines in progress.Total FHTC to be given 2991 in the whole panchayath,FHTC given-308.Distribution lines for half of the panchayath(2 zones out of 4 zones) and production components for the scheme is arranged as KIIFB work. |
Piravam Project Sub Dn AE 2 |
|
24 Aug 2023 |
Work is under good progress.Pipe laying through Kaliyar Kakkadassery KSTP road completed.Laying of distribution lines through panchayath roads in good progress.Interconnection works of already laid lines in progress.Total FHTC to be given 2991 in the whole panchayath,FHTC given-308.Distribution lines for half of the panchayath(2 zones out of 4 zones) and production components for the scheme is arranged as KIIFB work. |
Piravam Project Sub Dn AE 2 |
|
17 Aug 2023 |
Work is under good progress.Pipe laying through Kaliyar Kakkadassery KSTP road completed.Laying of distribution lines through panchayath roads in good progress.Interconnection works of already laid lines in progress.Total FHTC to be given 2991 in the whole panchayath,FHTC given-308.Distribution lines for half of the panchayath(2 zones out of 4 zones) and production components for the scheme is arranged as KIIFB work. |
Piravam Project Sub Dn AE 2 |
|
11 Aug 2023 |
Work is under good progress.Pipe laying through Kaliyar Kakkadassery KSTP road completed.Laying of distribution lines through panchayath roads in good progress.Interconnection works of already laid lines in progress.Total FHTC to be given 2991 in the whole panchayath,FHTC given-308.Distribution lines for half of the panchayath(2 zones out of 4 zones) and production components for the scheme is arranged as KIIFB work. |
Piravam Project Sub Dn AE 2 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
28/03/2022 |
Scheduled date of Completion of the Project |
31 Mar 2023 |
Expected date of Completion |
31/03/2023 |
Processing Dates
AS Date |
18 Sep 2021 |
TS Date |
07 Dec 2021 |