Name of the Work : DEPOSIT WORK DISTRICT PANCHAYATH EXTENTION OF PIPE LINE KANJIRATHANAM PARAMBRAM DRINKING WATER SUPPLY PROJECT AT MANJOOR PANCHAYATH

Project Name of the Work : DEPOSIT WORK DISTRICT PANCHAYATH EXTENTION OF PIPE LINE KANJIRATHANAM PARAMBRAM DRINKING WATER SUPPLY PROJECT AT MANJOOR PANCHAYATH
Project Code KTMDEPO03218123
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Name of the Work : DEPOSIT WORK DISTRICT PANCHAYATH EXTENTION OF PIPE LINE KANJIRATHANAM PARAMBRAM DRINKING WATER SUPPLY PROJECT AT MANJOOR PANCHAYATH
Status Completed
District Kottayam
Executing Office Kaduthuruthy PH Dn
AS Amount (Rs) 500000
AS Number A2-700/21
TS Amount (Rs) 500000
TS Number TS/2021-2022/2021/3915 Dated: 17-04-2021
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 78
Capacity in MLD 0.00
Actual Project Completion Date 31 Aug 2021
Coverage DEPOSIT WORK DISTRICT PANCHAYATH EXTENTION OF PIPE LINE KANJIRATHANAM PARAMBRAM DRINKING WATER SUPPLY PROJECT AT MANJOOR PANCHAYATH
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Name of the Work : DEPOSIT WORK DISTRICT PANCHAYATH EXTENTION OF PIPE LINE KANJIRATHANAM PARAMBRAM DRINKING WATER SUPPLY PROJECT AT MANJOOR PANCHAYATH Kaduthuruthy Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
18 Dec 2021 work completed.Bill submitted to Division office Kaduthuruthy Dn EE
17 Dec 2021 work completed.Bill scrutining under SubDvision Kaduthuruthy Dn EE
16 Dec 2021 work completed.Bill under preparation Kaduthuruthy Dn EE
15 Dec 2021 work completed.Bill under preparation Kaduthuruthy Dn EE
14 Dec 2021 work completed.Bill under preparation Kaduthuruthy Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 27/07/2021
Scheduled date of Completion of the Project 26 Sep 2021
Expected date of Completion 31/12/2021

Processing Dates

AS Date 20 Mar 2021
TS Date 17 Apr 2021