Deposit Work Vazhathope GP 257/2021-2022-Mulakuvally St.Antony's Road Water Supply Project

Project Deposit Work Vazhathope GP 257/2021-2022-Mulakuvally St.Antony's Road Water Supply Project
Project Code IDKDEPO062212073
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Deposit Work Vazhathope GP 257/2021-2022-Mulakuvally St.Antony's Road Water Supply Project
Status Completed
District Idukki
Executing Office Painavu Sn
AS Amount (Rs) 332000
AS Number A4-120/22
TS Amount (Rs) 332000
TS Number 8823/2022-2023
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 100
Capacity in MLD 0.00
Actual Project Completion Date Date is not specified
Coverage Mulakuvally Area

Packages

No. Project Name Location View
1 Deposit Work Vazhathope GP 257/2021-2022-Mulakuvally St.Antony's Road Water Supply Project Painavu Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 Oct 2023 Work Completed Painavu PH Section AE
10 Oct 2023 KSTP denied permission for road cutting and pipe laying citing that road is under DLP. But DLP period is not mentioned yet. Route change is discussed with concerned Ward member. Waiting for permission from Panchayath Painavu PH Section AE
03 Oct 2023 KSTP denied permission for road cutting and pipe laying citing that road is under DLP. But DLP period is not mentioned yet. Route change is discussed with concerned Ward member. Waiting for permission from Panchayath Painavu PH Section AE
27 Sep 2023 KSTP denied permission for road cutting and pipe laying citing that road is under DLP. But DLP period is not mentioned yet. Route change is discussed with concerned Ward member. Waiting for permission from Panchayath Painavu PH Section AE
20 Sep 2023 KSTP denied permission for road cutting and pipe laying citing that road is under DLP. But DLP period is not mentioned yet. Route change is discussed with concerned Ward member. Waiting for permission from Panchayath Painavu PH Section AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 27/08/2022
Scheduled date of Completion of the Project 25 Feb 2023
Expected date of Completion 17/10/2023

Processing Dates

AS Date 06 Jun 2022
TS Date 30 Jun 2022

Other details

Project Officers View