Deposit Work Vazhathope GP 257/2021-2022-Mulakuvally St.Antony's Road Water Supply Project
| Project |
Deposit Work Vazhathope GP 257/2021-2022-Mulakuvally St.Antony's Road Water Supply Project |
| Project Code |
IDKDEPO062212073 |
| Type |
Main project |
| Funding Agency |
DEPO |
| Category |
Deposit Work |
| Type of scheme |
Water Supply |
| Scheme |
DEPO |
| Description |
Deposit Work Vazhathope GP 257/2021-2022-Mulakuvally St.Antony's Road Water Supply Project
|
| Status |
Completed |
| District |
Idukki |
| Executing Office |
Painavu Sn |
| AS Amount (Rs) |
332000
|
| AS Number |
A4-120/22 |
| TS Amount (Rs) |
332000 |
| TS Number |
8823/2022-2023 |
| Total Bill Submitted (Rs) |
0 |
| Total Bill Paid (Rs) |
0 |
| Population Benefitted |
100 |
| Capacity in MLD |
0.00 |
| Actual Project Completion Date |
Date is not specified |
| Coverage |
Mulakuvally Area |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
Deposit Work Vazhathope GP 257/2021-2022-Mulakuvally St.Antony's Road Water Supply Project |
Painavu Sn |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 17 Oct 2023 |
Work Completed |
Painavu PH Section AE |
|
| 10 Oct 2023 |
KSTP denied permission for road cutting and pipe laying citing that road is under DLP. But DLP period is not mentioned yet. Route change is discussed with concerned Ward member. Waiting for permission from Panchayath |
Painavu PH Section AE |
|
| 03 Oct 2023 |
KSTP denied permission for road cutting and pipe laying citing that road is under DLP. But DLP period is not mentioned yet. Route change is discussed with concerned Ward member. Waiting for permission from Panchayath |
Painavu PH Section AE |
|
| 27 Sep 2023 |
KSTP denied permission for road cutting and pipe laying citing that road is under DLP. But DLP period is not mentioned yet. Route change is discussed with concerned Ward member. Waiting for permission from Panchayath |
Painavu PH Section AE |
|
| 20 Sep 2023 |
KSTP denied permission for road cutting and pipe laying citing that road is under DLP. But DLP period is not mentioned yet. Route change is discussed with concerned Ward member. Waiting for permission from Panchayath |
Painavu PH Section AE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
27/08/2022 |
| Scheduled date of Completion of the Project |
25 Feb 2023 |
| Expected date of Completion |
17/10/2023 |
Processing Dates
| AS Date |
06 Jun 2022 |
| TS Date |
30 Jun 2022 |