Project | KIIFB -WRD 002-11- WSS TO MATTANNUR & IRITTY MUNICIPALITIES -PACAKGE III |
---|---|
Project Code | KNRKIIFB0117528P3 |
Type | Package |
Main Project | KIIFB -WRD 002-11 -WSS TO MATTANNUR AND IRITTY MUNICIPALITIES |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | Construction of 15LL capacity OHSR at Kotheri and Clear Water Gravity Main from GLSR Chavasseriparamba to OH tank at Kotheri (400mm DI 8590m. ) |
Status | On-going |
District | Kannur |
Executing Office | Mattannur Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 107400000 |
TS Number | KWA/CE/NR/D2-3971/2017 |
Technical specification | Construction of 15LL capacity OHSR at Kotheri and Clear Water Gravity Main from GLSR Chavasseriparamba to OH tank at Kotheri. |
Contractor | Thomas K Paul (Mob: 9447061604) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 07/03/2018 |
---|---|
Scheduled date of Completion as per agreement | 06 Mar 2019 |
Expected date of Completion | 31/08/2019 |
TS Date | 12 Dec 2017 |
---|---|
Estimate Approval | 12 Dec 2017 |
Tender Closing | 09 Jan 2018 |
Price bid opening | 12 Jan 2018 |
Workorder Date | 07 Mar 2018 |
---|---|
NA | 23 Mar 2018 |
Mattannur Project Sn 2 AE |
Date: 24/08/2021 |
Work has been completed | 100% Completed
Final bill approved by KIIFB on 19/08/2021.
Mattannur Project Sn 2 AE |
Date: 19/02/2021 |
Work has been completed | 100% Completed
Completed.