JJM-Phase II-Providing Balance FHTC in Velinaloor panchayath and distribution network with the construction of 7.00 LL OHSR

Project JJM-Phase II-Providing Balance FHTC in Velinaloor panchayath and distribution network with the construction of 7.00 LL OHSR
Project Code KLMJJM09218611P1
Type Package
Main Project JJM-Phase II-Providing Balance FHTC in Velinaloor panchayath and distribution network with the construction of 7.00 LL OHSR
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Providing Balance FHTC in Velinaloor panchayath, providing distribution network with the construction of 7.00 LL OHSR
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 354700000
TS Number TS/2021-2022/2021/37318
Technical specification providing balance FHTC and distribution network of 121 km,Construction of 7LL OHSR at Attorkonam.
Contractor Sivaprasad S (Mob: 9447206962)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 13/05/2022
Scheduled date of Completion as per agreement 12 May 2023
Expected date of Completion 12/05/2023

Processing Dates

TS Date 18 Nov 2021
Estimate Approval 18 Nov 2021
NIT Approval 18 Sep 2021
Tender Closing 03 Mar 2022
Technichal Pre-Qualification 07 Mar 2022
Price bid opening 09 Mar 2022

Approval Dates

Workorder Date 19 Mar 2022
NA 13 May 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project HD
Date: 27/06/2024

Work in progress | 82% Completed

7LL OHSR -Completed. FHTCs -1205 Numbers completed. 200mm DI K9 CWPM - Pipe laying work in progress, 5500m laying completed. Distribution network - Pipe laying work in progress, 136km complete..

Kollam Project HD
Date: 26/06/2024

Work in progress | 82% Completed

7LL OHSR -Completed. FHTCs -1205 Numbers completed. 200mm DI K9 CWPM - Pipe laying work in progress, 5500m laying completed. Distribution network - Pipe laying work in progress, 136km complete..