Project | JJM-Phase II-Providing Balance FHTC in Velinaloor panchayath and distribution network with the construction of 7.00 LL OHSR |
---|---|
Project Code | KLMJJM09218611P1 |
Type | Package |
Main Project | JJM-Phase II-Providing Balance FHTC in Velinaloor panchayath and distribution network with the construction of 7.00 LL OHSR |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Providing Balance FHTC in Velinaloor panchayath, providing distribution network with the construction of 7.00 LL OHSR |
Status | On-going |
District | Kollam |
Executing Office | Kollam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 354700000 |
TS Number | TS/2021-2022/2021/37318 |
Technical specification | providing balance FHTC and distribution network of 121 km,Construction of 7LL OHSR at Attorkonam. |
Contractor | Sivaprasad S (Mob: 9447206962) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 13/05/2022 |
---|---|
Scheduled date of Completion as per agreement | 12 May 2023 |
Expected date of Completion | 12/05/2023 |
TS Date | 18 Nov 2021 |
---|---|
Estimate Approval | 18 Nov 2021 |
NIT Approval | 18 Sep 2021 |
Tender Closing | 03 Mar 2022 |
Technichal Pre-Qualification | 07 Mar 2022 |
Price bid opening | 09 Mar 2022 |
Workorder Date | 19 Mar 2022 |
---|---|
NA | 13 May 2022 |
Kollam Project HD |
Date: 27/06/2024 |
Work in progress | 82% Completed
7LL OHSR -Completed. FHTCs -1205 Numbers completed. 200mm DI K9 CWPM - Pipe laying work in progress, 5500m laying completed. Distribution network - Pipe laying work in progress, 136km complete..
Kollam Project HD |
Date: 26/06/2024 |
Work in progress | 82% Completed
7LL OHSR -Completed. FHTCs -1205 Numbers completed. 200mm DI K9 CWPM - Pipe laying work in progress, 5500m laying completed. Distribution network - Pipe laying work in progress, 136km complete..