STATE PLAN-2019-20 ARWSS TO PULIYANOOR MEENACHIL AND AKALAKUNNAM VILLAGES - REPLACEMENT OF PUMP SET, SUPPLY , ERECTION AND COMMISSIONING OF 50HP, CENTRIFUGAL MULTI STAGE PUMP SET TO MALAYIRUTHY TANK FROM MUTHOLY WTP

Project STATE PLAN-2019-20 ARWSS TO PULIYANOOR MEENACHIL AND AKALAKUNNAM VILLAGES - REPLACEMENT OF PUMP SET, SUPPLY , ERECTION AND COMMISSIONING OF 50HP, CENTRIFUGAL MULTI STAGE PUMP SET TO MALAYIRUTHY TANK FROM MUTHOLY WTP
Project Code KTMGOK06191065P1
Type Package
Main Project STATE PLAN-2019-20 ARWSS TO PULIYANOOR MEENACHIL AND AKALAKUNNAM VILLAGES - REPLACEMENT OF PUMP SET, SUPPLY , ERECTION AND COMMISSIONING OF 50HP, CENTRIFUGAL MULTI STAGE PUMP SET TO MALAYIRUTHY TANK FROM MUTHOLY WTP
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description STATE PLAN-2019-20 ARWSS TO PULIYANOOR MEENACHIL AND AKALAKUNNAM VILLAGES - REPLACEMENT OF PUMP SET, SUPPLY , ERECTION AND COMMISSIONING OF 50HP, CENTRIFUGAL MULTI STAGE PUMP SET TO MALAYIRUTHY TANK FROM MUTHOLY WTP
Status Completed
District Kottayam
Executing Office Pala WS Sn
Agreement Number
Agreement Date
TS Amount (Rs) 870000
TS Number TS/2019-2020/2019/4151
Technical specification Supply erection & commissioning of 50 HP pumpset

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 15/09/2021
Scheduled date of Completion as per agreement 16 Sep 2021
Expected date of Completion 15/09/2021

Processing Dates

TS Date 04 Oct 2019
Estimate Approval 04 Oct 2019
NIT Approval 04 Oct 2019
Tender Closing 31 May 2021
Technichal Pre-Qualification 04 Oct 2019
Price bid opening 14 Apr 2021

Approval Dates

Workorder Date 03 May 2021
NA 17 Jun 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kottayam PH Dn EE
Date: 21/01/2022

Work has been completed | 100% Completed

Work completed and Bill submitted.

Kottayam PH Dn EE
Date: 18/01/2022

Work has been completed | 100% Completed

Work completed and Bill submitted.