Jal Jeevan Mission-Providing house hold retrofittable/extendable water service connection in Manannchery Panchayath in Alappuzha District

Project Jal Jeevan Mission-Providing house hold retrofittable/extendable water service connection in Manannchery Panchayath in Alappuzha District
Project Code ALPJJM022213380P1
Type Package
Main Project Jal Jeevan Mission-Providing house hold retrofittable/extendable water service connection in Manannchery Panchayath in Alappuzha District
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission-Providing house hold retrofittable/extendable water service connection in Manannchery Panchayath in Alappuzha District
Status On-going
District Alappuzha
Executing Office KIIFB Projects (ALP)
Agreement Number
Agreement Date
TS Amount (Rs) 177370000
TS Number WRD/KWA-CE(CR)/EST_TS/3007/2022_26_1_1
Technical specification Providing house hold retrofittable/extendable water service connection in Manannchery Panchayath in Alappuzha District No of FHTC to be given -11213 Details of Pipes to be laid 90 mm HDPE -18 Km 110 mm HDPE-7.05 Km

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 19/01/2023
Scheduled date of Completion as per agreement 18 Jan 2024
Expected date of Completion 18/01/2024

Processing Dates

TS Date 23 Aug 2022
Estimate Approval 23 Aug 2022
NIT Approval 27 Nov 2022
Tender Closing 08 Nov 2022
Technichal Pre-Qualification 01 Dec 2022
Price bid opening 04 Jan 2023

Approval Dates

Workorder Date 19 Jan 2023
NA 02 Feb 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Alappuzha KIIFB - AE 4
Date: 29/06/2024

Work in progress | 45% Completed

Pipe laying work progressing. Total laid length of 90mm HDPE 17999.20 m and 110mm HDPE 7049.30m.Total FHTC -4226Nos.CC XIth and part bill claimed for 476 Nos. Total claimed 4294Nos. Billed HTC 476 Nos..

Alappuzha KIIFB - AE 4
Date: 28/06/2024

Work in progress | 45% Completed

Pipe laying work progressing. Total laid length of 90mm HDPE 17999.20 m and 110mm HDPE 7049.30m.Total FHTC -4226Nos.CC XIth and part bill claimed for 476 Nos. Total claimed 4294Nos. Billed HTC 476 Nos..