Kasaragod District-WSS to Ajanur,Pallikkara,Udma, Pullur Periya Panchayats and Kolathur village in Bedadka Panchayth-

Project Kasaragod District-WSS to Ajanur,Pallikkara,Udma, Pullur Periya Panchayats and Kolathur village in Bedadka Panchayth-
Project Code KGDJJM022215646
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Kasaragod District-WSS to Ajanur,Pallikkara,Udma, Pullur Periya Panchayats and Kolathur village in Bedadka Panchayth.
Status On-going
District Kasaragod
Executing Office Kanhangad Project Division
AS Amount (Rs) 2688272000
AS Number G.O.(Rt)No.134/2022/WRD & G.O.(Rt)No.489/2021/WRD
TS Amount (Rs) 349800000
TS Number WRD/KWA-CE(NR)/EST_TS/669/2022_5_1_1 Dated: 11-04-2023
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 Package - 6- Construction of 12LL Capacity OHSR & Laying Distribution system and providing FHTCs in lower level of PullurPeriya Panchayth Kanhangad Project Division
2 Package - 7 - Construction of 5LL Capacity OHSR at Kaikottkunn-Laying Distribution System Providing FHTCs in upper level of PullurPeriya PanchaythPackage - 7 - Construction of 5LL Capacity OHSR at Kaikottkunn-Laying Distribution System Providing FHTCs in upper level of PullurPeriya Panchayth Kanhangad Project Division

Overall Project Status

Status Date Overall Project Status Project Officer Contact
15 May 2024 Work in progress at lower part of Pullur Periya Panchayath( Package 06) Kanhangad Proj Dn AE - 2
02 May 2024 Work in progress at lower part of Pullur Periya Panchayath( Package 06) Kanhangad Proj Dn AE - 2
30 Apr 2024 Work in progress at lower part of Pullur Periya Panchayath( Package 06) Kanhangad Proj Dn AE - 2
29 Apr 2024 work has started(package 06). Kanhangad Proj Dn AE - 2

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion Date is not specified

Processing Dates

AS Date 23 Feb 2022
TS Date 11 Apr 2023

Other details

Project Officers View