JJM DER 2020-21 THOLICODE GRAMA PANCHAYATH PIPE LINE EXTENSIONS AND PROVIDING HOUSE CONNECIONS IN THOLICODE GRAMA PANCHAYATH PHASE II A3 2150 FHTCs FROM ONGOING SCHEME-PART 2.

Project JJM DER 2020-21 THOLICODE GRAMA PANCHAYATH PIPE LINE EXTENSIONS AND PROVIDING HOUSE CONNECIONS IN THOLICODE GRAMA PANCHAYATH PHASE II A3 2150 FHTCs FROM ONGOING SCHEME-PART 2.
Project Code TVMJJM08206675P11
Type Package
Main Project JJM (2020-2021)- Tholicode Grama Panchayath- Providing Functional Household Tap Connections- Phase I & II(Total AS-756 Lakhs- Aruvikkara Division Awarded-1571 FHTCS-232.2Lakhs & balance 6350 FHTCs for AS amount-523.8
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM DER 2020-21 THOLICODE GRAMA PANCHAYATH PIPE LINE EXTENSIONS AND PROVIDING HOUSE CONNECIONS IN THOLICODE GRAMA PANCHAYATH PHASE II A3 2150 FHTCs FROM ONGOING SCHEME-PART 2.
Status On-going
District Thiruvananthapuram
Executing Office Palod WS Sn
Agreement Number
Agreement Date
TS Amount (Rs) 22738000
TS Number 7442/2022-2023
Technical specification JJM DER 2020-21 THOLICODE GRAMA PANCHAYATH PIPE LINE EXTENSIONS AND PROVIDING HOUSE CONNECIONS IN THOLICODE GRAMA PANCHAYATH PHASE II A3 2150 FHTCs FROM ONGOING SCHEME-PART 2.
Contractor Anilkumar T R (Mob: 9446537754)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 18/11/2022
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion 17/05/2023

Processing Dates

TS Date 16 Jun 2022
Estimate Approval 16 Jun 2022
NIT Approval 16 Jun 2022
Tender Closing 21 Jun 2022
Technichal Pre-Qualification 30 Jun 2022
Price bid opening 09 Aug 2022

Approval Dates

Workorder Date 18 Nov 2022
NA 29 Nov 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Palode AE
Date: 01/07/2024

Work in progress | 93% Completed

work ongoing.

Palode AE
Date: 20/06/2024

Work in progress | 93% Completed

work ongoing.