- Home
- JJM - PHASE II- SUPPLY & LAYING DISTRIBU...
JJM - PHASE II- SUPPLY & LAYING DISTRIBUTION SYSTEM IN KADAPRA PANCHAYATHS ( BALANCE PART) & PROVIDING FHTC's
Project |
JJM - PHASE II- SUPPLY & LAYING DISTRIBUTION SYSTEM IN KADAPRA PANCHAYATHS ( BALANCE PART) & PROVIDING FHTC's |
Project Code |
PTAJJM09219301 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
SUPPLY & LAYING DISTRIBUTION SYSTEM IN KADAPRA PANCHAYATHS ( BALANCE PART) & PROVIDING FHTC's |
Status |
On-going |
District |
Pathanamthitta |
Executing Office |
Adoor Project Dn |
AS Amount (Rs) |
224600000
|
AS Number |
G.O.(Rt)No.489/2021/WRD |
TS Amount (Rs) |
192900000 |
TS Number |
TS/2021-2022/2021/3769 Dated: 06-12-2021 |
Total Bill Submitted (Rs) |
75658291 |
Total Bill Paid (Rs) |
75658291 |
Population Benefitted |
16800 |
Capacity in MLD |
13.00 |
Actual Project Completion Date |
03 Mar 2023 |
Coverage |
SUPPLY & LAYING DISTRIBUTION SYSTEM IN KADAPRA PANCHAYATHS ( BALANCE PART) & PROVIDING FHTC's |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM)-JJM KADAPRA-Laying balance distribution network and alteration of existing house connections-Pipeline Work |
Adoor Project Dn |
|
2 |
JJM- SUPPLY & LAYING DISTRIBUTION SYSTEM IN KADAPRA PANCHAYATHS ( BALANCE PART) & PROVIDING FHTC's |
Adoor Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
03 Oct 2022 |
Pipe supply completed. Pipe laying 40.15 km completed out of 46 KM. FHTC 1434 completed out of 4910.
|
Adoor Project Dn AE3 |
|
14 Sep 2022 |
Pipe supply completed. Pipe laying 40.15 km completed out of 46 KM. FHTC 1434 completed out of 4910. |
Adoor Project Dn AE3 |
|
18 Jul 2022 |
Pipe laying work in progress |
Adoor Project Dn AE3 |
|
10 Jul 2022 |
Pipe laying work in progress |
Adoor Project Dn AE3 |
|
28 Jun 2022 |
Supply of PE pipe completed. 1000 connections completed |
Adoor Project Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
04/03/2022 |
Scheduled date of Completion of the Project |
03 Mar 2023 |
Expected date of Completion |
15/01/2024 |
Processing Dates
AS Date |
18 Sep 2021 |
TS Date |
06 Dec 2021 |