Project | KIIFB-WSS to Thrissur Corporation and adjoining 17 panchayaths-Package 1 |
---|---|
Project Code | TCRKIIFB0117503P1 |
Type | Package |
Main Project | KIIFB-WSS to Thrissur Corporation and adjoining panchayaths |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | Components a) 12 m dia well cum pump house at Thirukuzhi b) RW Pump set-530HP (6nos 2nos standby) c) RWPM - 1320mm MS Pipe(15mm thick)- 3350m d) 1000kVA Transformer-2nos and structure & Irraction. e) Retaining wall at Intake Well site f) Water Treatment Plant 100 MLD (Super Pulsator technology) and providing SCADA arrangements g) Surge arrester in 1320mm Raw water pumping main h) Site levelling and retaining wall at WTP site i) Transformer at WTP Site j) Providing Fire Hydrant System |
Status | On-going |
District | Thrissur |
Executing Office | Nattika Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 0 |
TS Number | nil |
Technical specification | 12 m dia well cum pump house at Thirukuzhi b) RW Pump set-530HP (6nos 2nos standby) c) RWPM - 1320mm MS Pipe(15mm thick)- 3350m d) 1000kVA Transformer-2nos and structure e) Retaining wall at Intake Well site f) Water Treatment Plant 100 MLD (Super Pulsator technology) and providing SCADA arrangements g) Surge arrester in 1320mm Raw water pumping main h) Site levelling and retaining wall at WTP site i) Transformer at WTP Site j) Providing Fire Hydrant System |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | Date is not specified |
---|---|
Scheduled date of Completion as per agreement | Date is not specified |
Expected date of Completion | Date is not specified |
Nattika Project Dn AE 4 |
Date: 18/03/2024 |
Work has started | 0% Completed
Estimate submitted for approval. .
Nattika Project Dn AE 4 |
Date: 17/03/2024 |
Work has started | 0% Completed
Estimate submitted for approval. .