Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

AMRUT-Construction of 5LL OHSR at Kuttanelloor, CWGM for 4.2KM with 250 mm DI and 6.1KM distribution line (Revised AS - 9.05 Cr.)

Project AMRUT-Construction of 5LL OHSR at Kuttanelloor, CWGM for 4.2KM with 250 mm DI and 6.1KM distribution line (Revised AS - 9.05 Cr.)
Project Code TCRGOI0318532
Type Main project
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description 1. 250mm DI K9 clear water gravity main (4272mm) 2. Supply and erection of clear water centrifugal motor & pumpsets (30HP-2 No's) 3. Constuction of 5LL clear water sump cum OHSR 4. Power connection & distribuition system -6116m
Status On-going
District Thrissur
Executing Office Nattika Project Dn
AS Amount (Rs) 90500000
AS Number Go(Rt)No.1951/2021/LSGD
TS Amount (Rs) 80000000
TS Number KWA/CE/CR/NTA/973/2018/D6 Kochi, Dated:15.03.2018
Total Bill Submitted (Rs) 59797623
Total Bill Paid (Rs) 59693174
Population Benefitted 8150
Capacity in MLD 1.85
Actual Project Completion Date Date is not specified
Coverage This project is intended to provide adequate drinking water facility for Kuttanellur Division of Thrissur Corporation.The ultimate population is 8100 in year 2050 and the corresponding water demand comes to 150 lpcd.
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 AMRUT-Construction of 5LL OHSR at Kuttanelloor, CWGM for 4.2KM with 250 mm DI and 6.1KM distribution line Nattika Project Dn
2 AMRUT-Construction of 5LL OHSR at Kuttanellur Nattika Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
19 Feb 2024 Package II: Pile foundation(16 nos), pile load test ,earthwork excavation, Pile cap, plinth beam/tie beam earth filling completed. Ground floor - pump house column with stair ( 3 flight),Ground floor- pump house roof beam with roof slab,First floor- column ,stair (3 flight),brace beam,Second floor - column,stair(2 flight) completed.Second brace beam concrete work completed.Haunch & shoe concreting work completed.column reinforcement work completed.column shuttering work completed.column concreting first lift completed.Second lift shuttering work completed.Second lift column concreting completed.Tank floor slab,shuttering,beam reinforcement and ceiling plastering work completed. Bottom slab, beam &walkway concreting work completed. Stair concreting work completed. Side wall first lift concreting work completed. Side wall second lift concreting work completed. Side wall third lift concreting work completed. Side wall fourth lift concreting work completed (0.6m). Roof slab concreting completed. Hand rail work and roof slab deshuttering work completed. 90% Plastering work completed. Hand rail work completed. Compound wall foundation work completed. Compound wall solid brick work completed. Compound wall plastering completed. Septic tank work ongoing. Inside wall plastering ongoing. Nattika Project Dn AE 5
17 Feb 2024 Package II: Pile foundation(16 nos), pile load test ,earthwork excavation, Pile cap, plinth beam/tie beam earth filling completed. Ground floor - pump house column with stair ( 3 flight),Ground floor- pump house roof beam with roof slab,First floor- column ,stair (3 flight),brace beam,Second floor - column,stair(2 flight) completed.Second brace beam concrete work completed.Haunch & shoe concreting work completed.column reinforcement work completed.column shuttering work completed.column concreting first lift completed.Second lift shuttering work completed.Second lift column concreting completed.Tank floor slab,shuttering,beam reinforcement and ceiling plastering work completed. Bottom slab, beam &walkway concreting work completed. Stair concreting work completed. Side wall first lift concreting work completed. Side wall second lift concreting work completed. Side wall third lift concreting work completed. Side wall fourth lift concreting work completed (0.6m). Roof slab concreting completed. Hand rail work and roof slab deshuttering work completed. 90% Plastering work completed. Hand rail work completed. Compound wall foundation work completed. Compound wall solid brick work completed. Compound wall plastering completed. Septic tank work ongoing. Nattika Project Dn AE 5
16 Feb 2024 Package II: Pile foundation(16 nos), pile load test ,earthwork excavation, Pile cap, plinth beam/tie beam earth filling completed. Ground floor - pump house column with stair ( 3 flight),Ground floor- pump house roof beam with roof slab,First floor- column ,stair (3 flight),brace beam,Second floor - column,stair(2 flight) completed.Second brace beam concrete work completed.Haunch & shoe concreting work completed.column reinforcement work completed.column shuttering work completed.column concreting first lift completed.Second lift shuttering work completed.Second lift column concreting completed.Tank floor slab,shuttering,beam reinforcement and ceiling plastering work completed. Bottom slab, beam &walkway concreting work completed. Stair concreting work completed. Side wall first lift concreting work completed. Side wall second lift concreting work completed. Side wall third lift concreting work completed. Side wall fourth lift concreting work completed (0.6m). Roof slab concreting completed. Hand rail work and roof slab deshuttering work completed. 90% Plastering work completed. Hand rail work completed. Compound wall foundation work completed. Compound wall solid brick work ongoing. Nattika Project Dn AE 5
15 Feb 2024 Package II: Pile foundation(16 nos), pile load test ,earthwork excavation, Pile cap, plinth beam/tie beam earth filling completed. Ground floor - pump house column with stair ( 3 flight),Ground floor- pump house roof beam with roof slab,First floor- column ,stair (3 flight),brace beam,Second floor - column,stair(2 flight) completed.Second brace beam concrete work completed.Haunch & shoe concreting work completed.column reinforcement work completed.column shuttering work completed.column concreting first lift completed.Second lift shuttering work completed.Second lift column concreting completed.Tank floor slab,shuttering,beam reinforcement and ceiling plastering work completed. Bottom slab, beam &walkway concreting work completed. Stair concreting work completed. Side wall first lift concreting work completed. Side wall second lift concreting work completed. Side wall third lift concreting work completed. Side wall fourth lift concreting work completed (0.6m). Roof slab concreting completed. Hand rail work and roof slab deshuttering work completed. 90% Plastering work completed. Hand rail work completed. Compound wall foundation work ongoing. Nattika Project Dn AE 5
14 Feb 2024 Package II: Pile foundation(16 nos), pile load test ,earthwork excavation, Pile cap, plinth beam/tie beam earth filling completed. Ground floor - pump house column with stair ( 3 flight),Ground floor- pump house roof beam with roof slab,First floor- column ,stair (3 flight),brace beam,Second floor - column,stair(2 flight) completed.Second brace beam concrete work completed.Haunch & shoe concreting work completed.column reinforcement work completed.column shuttering work completed.column concreting first lift completed.Second lift shuttering work completed.Second lift column concreting completed.Tank floor slab,shuttering,beam reinforcement and ceiling plastering work completed. Bottom slab, beam &walkway concreting work completed. Stair concreting work completed. Side wall first lift concreting work completed. Side wall second lift concreting work completed. Side wall third lift concreting work completed. Side wall fourth lift concreting work completed (0.6m). Roof slab concreting completed. Hand rail work and roof slab deshuttering work completed. 90% Plastering work completed. Hand rail work completed. Nattika Project Dn AE 5

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 31/12/2018
Scheduled date of Completion of the Project 09 Dec 2019
Expected date of Completion 30/11/2023

Processing Dates

AS Date 08 Oct 2021
TS Date 15 Mar 2018

Other details

Project Officers View