Design, construction and commissioning of 3 MLD WTP, reservoir and pumping main for Ollukkara zone

Project Design, construction and commissioning of 3 MLD WTP, reservoir and pumping main for Ollukkara zone
Project Code TCRAMRUT03165821
Type Main project
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description Design, construction and commissioning of 3 MLD WTP, reservoir and pumping main for Ollukkara zone
Status On-going
District Thrissur
Executing Office Thrissur PH Dn
AS Amount (Rs) 140000000
AS Number Go (Rt). No.516/2018/LSGD
TS Amount (Rs) 28000000
TS Number WRD/KWA-CE(CR)/EST_TS/1780/2022_5_1_1
Total Bill Submitted (Rs) 441586
Total Bill Paid (Rs) 441586
Population Benefitted 50000
Capacity in MLD 3.00
Actual Project Completion Date Date is not specified
Coverage Ollukkara Zone
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 AMRUT- Design construction and commissioning of 3 MLD WTP, Reservoir and pumping main for Ollukkara zone in Thrissur Corporation- Construction of 3 MLD WTP and 10LL OH Tank at Mulayam Thrissur WW Sn 1
2 AMRUT- Design construction and commissioning of 3 MLD WTP, Reservoir and pumping main for Ollukkara zone in Thrissur Corporation- Construction of Intake well cum pumphouse and providing 250mm DI pumping line from intake well to plant.- Package 1 Thrissur WW Sn 1
3 AMRUT- Design construction and commissioning of 3 MLD WTP, Reservoir and pumping main for Ollukkara zone in Thrissur Corporation-Providing clear water distribution main of 350mm DI pipe Thrissur WW Sn 1
4 AMRUT - Design, construction and commissioning of 3 MLD WTP, reservoir and pumping main for Ollukkara zone in Thrissur Corporation-soil bore test Thrissur WW Sn 1

Overall Project Status

Status Date Overall Project Status Project Officer Contact
02 May 2024 Work in progress. Thrissur PH Dn EE
12 Apr 2024 Providing clear water distribution main of 350mm DI pipe-80%-Pipe laying work in progress, PKG-1-85%- Pump house brick work completed, Roof slab shuttering work completed Thrissur PH Dn EE
06 Apr 2024 Providing clear water distribution main of 350mm DI pipe-80%-Pipe laying work in progress, PKG-1-85%- Pump house brick work completed, Roof slab shuttering work completed Thrissur PH Dn EE
02 Apr 2024 Providing clear water distribution main of 350mm DI pipe-80%-Pipe laying work in progress, PKG-1-85%- Pump house brick work completed, Roof slab shuttering work completed Thrissur PH Dn EE
30 Mar 2024 Providing clear water distribution main of 350mm DI pipe-80%-Pipe laying work in progress, PKG-1-85%- Pump house brick work completed, Roof slab shuttering work completed Thrissur WW Sn - AE 1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 28/11/2022
Scheduled date of Completion of the Project 30 Dec 2023
Expected date of Completion 31/05/2024

Processing Dates

AS Date 22 Feb 2018
TS Date 28 Sep 2022

Other details