- Home
- Deposit Work Kumily Grama Panchayth :- A...
Deposit Work Kumily Grama Panchayth :- Annual Plan 2020-21 .Extension of Pipe Line at Ottakathalamedu colony in Ward 6 in Kumily Grama Panchayath . ( Project No 219)
| Project |
Deposit Work Kumily Grama Panchayth :- Annual Plan 2020-21 .Extension of Pipe Line at Ottakathalamedu colony in Ward 6 in Kumily Grama Panchayath . ( Project No 219) |
| Project Code |
IDKDEPO02218777 |
| Type |
Main project |
| Funding Agency |
DEPO |
| Category |
Deposit Work |
| Type of scheme |
Water Supply |
| Scheme |
DEPO |
| Description |
Deposit Work Kumily Grama Panchayth :- Annual Plan 2020-21 .Extension of Pipe Line at Ottakathalamedu colony in Ward 6 in Kumily Grama Panchayath . ( Project No 219) |
| Status |
Completed |
| District |
Idukki |
| Executing Office |
Kumily PH Section |
| AS Amount (Rs) |
100000
|
| AS Number |
219 |
| TS Amount (Rs) |
97620 |
| TS Number |
22061/2024-2025 |
| Total Bill Submitted (Rs) |
0 |
| Total Bill Paid (Rs) |
0 |
| Population Benefitted |
500 |
| Capacity in MLD |
4.50 |
| Actual Project Completion Date |
05 Aug 2025 |
| Coverage |
Ottakathalamedu colony |
| Implementation Schedule |
Download |
| Work Plan |
Download |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
Deposit Work Kumily Grama Panchayth :- Annual Plan 2020-21 .Extension of Pipe Line at Ottakathalamedu colony in Ward 6 in Kumily Grama Panchayath . ( Project No 219) |
Peerumedu Sn |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 05 Aug 2025 |
Final bill submitted |
Kumily PH Section - AE |
|
| 04 Jul 2025 |
Work completed. Bill under preparation. |
Kumily PH Section - AE |
|
| 05 Sep 2022 |
work on going |
Peerumedu Sn AE |
|
| 31 Aug 2022 |
work on going |
Peerumedu Sn AE |
|
| 29 Aug 2022 |
work on going
|
Peerumedu Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
03/02/2025 |
| Scheduled date of Completion of the Project |
02 Apr 2025 |
| Expected date of Completion |
02/04/2025 |
Processing Dates
| AS Date |
15 Feb 2021 |
| TS Date |
18 Dec 2024 |