| Project | SHIFTING OF EXISTING DISTRIBUTION PIPELINE FROM PARANKIMAVILA -MUTTATHU COLONY ROAD IN WARD4 OF MYNAGAPALLY GRAMAPANCHAYATH |
|---|---|
| Project Code | KLMDEPO032415916P1 |
| Type | Package |
| Main Project | DEPOSIT-RWSS TO MYNAGAPALLY--SHIFTING OF EXISTING DISTRIBUTION PIPELINE FROM PARANKIMAVILA -MUTTATHU COLONY ROAD IN WARD4 OF MYNAGAPALLY GRAMAPANCHAYATH |
| Funding Agency | DEPO |
| Category | Deposit Work |
| Type of scheme | Water Supply |
| Scheme | DEPO |
| Description | SHIFTING OF EXISTING DISTRIBUTION PIPELINE FROM PARANKIMAVILA -MUTTATHU COLONY ROAD IN WARD4 OF MYNAGAPALLY GRAMAPANCHAYATH |
| Status | On-going |
| District | Kollam |
| Executing Office | Sasthamcottah WS Sn2 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | |
| TS Number | |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 18/05/2024 |
|---|---|
| Scheduled date of Completion as per agreement | Date is not specified |
| Expected date of Completion | 25/05/2024 |
| Sasthamcotta WS Sn 2 HW - AE |
| Date: 01/06/2024 |
Work has been completed | 100% Completed
work completed and bill submitted.
| Sasthamcotta WS Sn 2 HW - AE |
| Date: 30/05/2024 |
Work has been completed | 100% Completed
work completed and bill submitted.