| Project | JJM - WSS to Tanur Municipality and adjoining 4 Panchayaths -phase-2 -Laying Transmission Main, Distribution Network and FHTCs in Niramaruthur Panchayath |
|---|---|
| Project Code | MLPJJM092112043P1 |
| Type | Package |
| Main Project | JJM - WSS to Tanur Municipality and adjoining 4 Panchayaths -phase-2 -Laying Transmission Main, Distribution Network and FHTCs in Niramaruthur Panchayath |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Laying distribution network and providing of FHTCs |
| Status | On-going |
| District | Malappuram |
| Executing Office | Malappuram Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 574800000 |
| TS Number | TS/2021-2022/2021/36474 |
| Technical specification | Laying distribution network and providing of FHTCs |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | Date is not specified |
|---|---|
| Scheduled date of Completion as per agreement | Date is not specified |
| Expected date of Completion | Date is not specified |
| TS Date | 08 Dec 2021 |
|---|---|
| Estimate Approval | 08 Dec 2021 |
| Malappuram Project Dn AE2 |
| Date: 24/04/2026 |
Work in progress | 38% Completed
The work was delayed due to non availability of road cuting permission from the PWD. 53 Km of pipeline CompletedPipeline and Connections Work in Progress 400 mm DI-315m,300 mm DI-657m,250 mm DI-912m,200 mm DI-1094m,75 mm HDPE-10000m.90 mm HDPE-41315m,110 mm HDPE-7000m,140 mm HDPE-3743m,160 mm HDPE-1368,80 mm GI-1000m,125 mm GI-186m,150 mm GI-120m.Pipe laid till date:-(GI,DI,PE)-50KM. HTC-2663 .Pipe line work and road restoration in panchayath roads were hindered by rain and waterlogging in trenches. Cutting of concrete road and main BT roads were hindered due to public protest. .
| Malappuram Project Dn AE2 |
| Date: 20/04/2026 |
Work in progress | 38% Completed
The work was delayed due to non availability of road cuting permission from the PWD. 53 Km of pipeline CompletedPipeline and Connections Work in Progress 400 mm DI-315m,300 mm DI-657m,250 mm DI-912m,200 mm DI-1094m,75 mm HDPE-10000m.90 mm HDPE-41315m,110 mm HDPE-7000m,140 mm HDPE-3743m,160 mm HDPE-1368,80 mm GI-1000m,125 mm GI-186m,150 mm GI-120m.Pipe laid till date:-(GI,DI,PE)-50KM. HTC-2663 .Pipe line work and road restoration in panchayath roads were hindered by rain and waterlogging in trenches. Cutting of concrete road and main BT roads were hindered due to public protest. .