Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM - WSS to Tanur Municipality and adjoining 4 Panchayaths -phase-2 -Laying Transmission Main, Distribution Network and FHTCs in Niramaruthur Panchayath

Project JJM - WSS to Tanur Municipality and adjoining 4 Panchayaths -phase-2 -Laying Transmission Main, Distribution Network and FHTCs in Niramaruthur Panchayath
Project Code MLPJJM092112043P1
Type Package
Main Project JJM - WSS to Tanur Municipality and adjoining 4 Panchayaths -phase-2 -Laying Transmission Main, Distribution Network and FHTCs in Niramaruthur Panchayath
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Laying distribution network and providing of FHTCs
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 574800000
TS Number TS/2021-2022/2021/36474
Technical specification Laying distribution network and providing of FHTCs

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion Date is not specified

Processing Dates

TS Date 08 Dec 2021
Estimate Approval 08 Dec 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Malappuram Project Dn AE2
Date: 24/04/2026

Work in progress | 38% Completed

The work was delayed due to non availability of road cuting permission from the PWD. 53 Km of pipeline CompletedPipeline and Connections Work in Progress 400 mm DI-315m,300 mm DI-657m,250 mm DI-912m,200 mm DI-1094m,75 mm HDPE-10000m.90 mm HDPE-41315m,110 mm HDPE-7000m,140 mm HDPE-3743m,160 mm HDPE-1368,80 mm GI-1000m,125 mm GI-186m,150 mm GI-120m.Pipe laid till date:-(GI,DI,PE)-50KM. HTC-2663 .Pipe line work and road restoration in panchayath roads were hindered by rain and waterlogging in trenches. Cutting of concrete road and main BT roads were hindered due to public protest. .

Malappuram Project Dn AE2
Date: 20/04/2026

Work in progress | 38% Completed

The work was delayed due to non availability of road cuting permission from the PWD. 53 Km of pipeline CompletedPipeline and Connections Work in Progress 400 mm DI-315m,300 mm DI-657m,250 mm DI-912m,200 mm DI-1094m,75 mm HDPE-10000m.90 mm HDPE-41315m,110 mm HDPE-7000m,140 mm HDPE-3743m,160 mm HDPE-1368,80 mm GI-1000m,125 mm GI-186m,150 mm GI-120m.Pipe laid till date:-(GI,DI,PE)-50KM. HTC-2663 .Pipe line work and road restoration in panchayath roads were hindered by rain and waterlogging in trenches. Cutting of concrete road and main BT roads were hindered due to public protest. .