Project | JJM (2021-2024) Phase II- Azhoor Grama Panchayath - Providing pipe line extension and providing Functional Household Tap Connections in Azhoor Panchayath |
---|---|
Project Code | TVMJJM09218673P1 |
Type | Package |
Main Project | JJM (2021-2024) Phase II- Azhoor Grama Panchayath - Providing pipe line extension and providing Functional Household Tap Connections in Azhoor Panchayath |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM (2021-2024) Phase II- Azhoor Grama Panchayath - Providing pipe line extension and providing Functional Household Tap Connections in Azhoor Panchayath |
Status | On-going |
District | Thiruvananthapuram |
Executing Office | Attingal WS Sn 1 |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 60200000 |
TS Number | TS/2021-2022/2021/11996 |
Technical specification | Providing pipe line extension and providing Functional Household Tap Connections |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | Date is not specified |
---|---|
Scheduled date of Completion as per agreement | 26 Nov 2022 |
Expected date of Completion | 30/08/2024 |
TS Date | 09 Dec 2021 |
---|---|
Estimate Approval | 09 Dec 2021 |
NIT Approval | 21 Dec 2021 |
Tender Closing | 21 Dec 2021 |
Technichal Pre-Qualification | 21 Dec 2021 |
Price bid opening | 23 Dec 2021 |
Workorder Date | 27 Jan 2022 |
---|---|
NA | 09 Feb 2022 |
Attingal WS Sn 1 - AE |
Date: 28/06/2024 |
Work in progress | 96% Completed
No work.
Attingal WS Sn 1 - AE |
Date: 25/06/2024 |
Work in progress | 96% Completed
No work.