Jal Jeevan Mission (JJM)-Phase III -WSS to Kanakkary, Mulakkulam and Njeezhoor panchayath (Njeezhoor-Package 1)-Pipeline Work

Project Jal Jeevan Mission (JJM)-Phase III -WSS to Kanakkary, Mulakkulam and Njeezhoor panchayath (Njeezhoor-Package 1)-Pipeline Work
Project Code KTMJJM022214628P1
Type Package
Main Project Jal Jeevan Mission (JJM)-Phase III -WSS to Kanakkary, Mulakkulam and Njeezhoor panchayath (Njeezhoor-Package 1)-Pipeline Work
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-Phase III -WSS to Kanakkary, Mulakkulam and Njeezhoor panchayath (Njeezhoor-Package 1)-Pipeline Work
Status On-going
District Kottayam
Executing Office Peruva Sn
Agreement Number
Agreement Date
TS Amount (Rs) 65500000
TS Number WRD/KWA-CEP/EST_TS/280/2022_26_2_1 Dated: 18-01-2023
Technical specification This estimate amounting Rs. 655.00 lakhs includes laying 12560 m 50 mm GI (M) pipes, 10511 m 80 mm GI(M) pipes, 3250 m 150 mm GI pipes, 900 m 100 mm GI pipes at various locations in Njeezhoor Panchayath,providing fhtc of 527 nos,using uPVC and PE pipes,road restoration works, relaying of existing 315mm PVC pipe with 300mm DI from Rajan Kavala to Jathikkamala OHSR (1500) and its road restoration works etc...
Contractor M D ASHOKAN (Mob: 9846248705)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 07/08/2023
Scheduled date of Completion as per agreement 04 Jan 2024
Expected date of Completion 04/01/2024

Processing Dates

TS Date 18 Jan 2023
Estimate Approval 18 Jan 2023
NIT Approval 18 Jan 2023
Tender Closing 22 May 2023
Technichal Pre-Qualification 01 Jun 2023
Price bid opening 06 Jun 2023

Approval Dates

Workorder Date 21 Jun 2023
NA 05 Jul 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kaduthuruthy Dn EE
Date: 28/06/2024

Work in progress | 52% Completed

No work .

Kaduthuruthy Dn EE
Date: 27/06/2024

Work in progress | 52% Completed

No work .